Catalyst 5000 Family Installation Guide (May 2000)
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Installing the Switch
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table of ContentsInstalling the SwitchInstalling the Switch
This chapter describes how to install the Catalyst 5000 family switch in a rack. For first-time installations, perform the procedures in the following sections in the order listed: For information on installing the supervisor engines and verifying switch operation, see Chapter 3, "Installing the Supervisor Engine," in the Catalyst 5000 Family Supervisor Engine Installation Guide.
Checking the Contents
To check the contents of the shipping container, follow these steps: Step 1 Check the contents of the accessories box against the Accessories Box Components Checklist and the packing slip. Verify that you received all listed equipment, which should include the following:
Step 2 Check the switching modules in each slot. Ensure that the configuration matches the packing list and that all the specified interfaces are included. Step 3 To begin installation, proceed to the "Rack-Mounting the Switch" section. Rack-Mounting the SwitchA standard rack-mount kit is included for mounting the switch in a standard 19-inch (48.3 cm) equipment rack with two unobstructed outer posts, with a minimum depth (between the front and rear mounting posts) of 19.25 inches (48.9 cm) and a maximum depth of 32 inches (81.3 cm). This kit is not suitable for use with racks with obstructions (such as a power strip) that could impair access to switch field-replaceable units (FRUs).
Rack-Mounting GuidelinesBefore rack-mounting the switch, ensure the following:
Lifting the Chassis SafelyTwo people are required to lift a Catalyst 5000, Catalyst 5505, Catalyst 5509, or Catalyst 5500 chassis. Whenever you lift the chassis or any heavy object, follow these guidelines:
The chassis is not intended to be moved frequently. Before you install the switch, ensure that your site is properly prepared so that you can avoid moving the chassis later to accommodate power sources and network connections. Required Installation ToolsThe following tools and equipment are required to install the chassis:
The following tools and equipment are required to install the chassis in a rack:
Rack-Mounting ProceduresProceed to the rack-mount installation procedure for the type of switch you are installing:
Rack-Mounting the Catalyst 5002 SwitchUse this procedure to install the Catalyst 5002 switch in a rack:
Step 1 Prepare for installation as follows: a. Place the chassis on the floor or on a sturdy table as close as possible to the rack. Leave enough clearance to allow you to move around the chassis. b. Use a tape measure to measure the depth of the rack. Measure from the outside of the front mounting posts to the outside of the rear mounting strip. The depth must be at least 19.25 inches (48.9 cm) but not greater than 32 inches (81.3 cm). c. Measure the space between the inner edges of the left front and right front mounting posts to ensure that it is 17.75 inches (45.09 cm) wide. (The chassis is 17.25 inches [43.8 cm] wide and must fit between the mounting posts.) d. Open the rack-mount kit and see the component checklist in Table 4-1 to verify that all parts are included. Table 4-1: Catalyst 5002 Switch: Rack-Mount Kit Checklist
Step 2 Note that the L brackets connect the chassis to the rack. You can mount the L brackets to the front or rear mounting holes of the chassis, depending on which end is in the front of the rack.
Attach the left and right L brackets using the four M4 Phillips pan-head screws provided in the rack-mount kit. (See Figure 4-1.) Figure 4-1: Catalyst 5002 Switch: Attaching the L Brackets
Step 3 Install the chassis in the rack as follows: a. Position the chassis in the rack as follows (see Figure 4-2):
b. Align the mounting holes in the L bracket with the mounting holes in the equipment rack. c. Secure the chassis using six (three per side) 12-24 x 3/4-inch screws through the elongated holes in the L bracket and into the threaded holes in the mounting post. d. Use a tape measure and level to ensure that the chassis is installed straight and level. Step 4 From the rear of the chassis, do the following: a. Check the ejector levers to ensure that the supervisor engine and the switching module are installed securely. b. Tighten any loose captive installation screws on the supervisor engine and switching module. Step 5 Note that the Catalyst 5002 switch powers up when you connect the power supply cords (do not power up the supplies at this point). Figure 4-2: Catalyst 5002 Switch: Installing the Switch in the Rack
Rack-Mounting the Catalyst 5000 and Catalyst 5505 SwitchesUse this procedure to install the Catalyst 5000 switch or Catalyst 5505 switch in a rack: Step 1 Prepare for installation as follows: a. Place the chassis on the floor or on a sturdy table as close as possible to the rack. Leave enough clearance to allow you to move around the chassis. b. Use a tape measure to measure the depth of the rack. Measure from the outside of the front mounting posts to the outside of the rear mounting strip. The depth must be at least 19.25 inches (48.9 cm) but not greater than 32 inches (81.3 cm). c. Measure the space between the inner edges of the left front and right front mounting posts to ensure that it is 17.75 inches (45.09 cm) wide. (The chassis is 17.25 inches [43.8 cm] wide and must fit between the mounting posts.) d. Open the rack-mount kit and use the checklist in Table 4-2 to verify that all parts are included. Table 4-2: Catalyst 5000 and Catalyst 5505 Switches: Rack-Mount Kit Checklist
Step 2 Note that the L brackets connect the chassis to the rack. Install the L brackets as follows: a. Remove the six screws from either the front or rear of the switch side cover panels, depending on which end of the chassis will be at the front of the rack. b. Attach the L brackets to the left and right sides of the chassis using the six M4 Phillips countersunk-head screws provided in the rack-mount kit. (See Figure 4-3.) Figure 4-3: Catalyst 5000 and Catalyst 5505 Switches: Attaching the L Brackets
c. Attach the cable guide, if needed, using the M3 screws provided in the cable management kit. The cable guide attaches to the L bracket. Attach the cable guide to the right side of the switch to prevent the cables from obscuring module LEDs. (See Figure 4-4.) Figure 4-4: Catalyst 5000 and Catalyst 5505 Switches: Attaching the Cable Guide
Step 3 Install the chassis in the rack as follows:
a. With a person standing at each side of the chassis, grasp the bottom edge of the chassis with one hand near the front and the other near the back. Slowly lift the chassis in unison. Avoid sudden twists or moves to prevent injury. b. Position the chassis in the rack as follows (see Figure 4-5):
c. Align the five L bracket mounting holes with the five front mounting post mounting holes. Figure 4-5: Catalyst 5000 and Catalyst 5505 Switches: Installing the Switch in the Rack
d. A third person should install the 10-32 x 3/4-inch slotted binder-head mounting screws through the elongated holes in the L bracket and into the threaded holes in the mounting post. e. Use a tape measure and level to ensure that the chassis is installed straight and level. Step 4 From the rear of the chassis, do the following: a. Check the ejector levers to ensure that the supervisor engine and all switching modules are securely installed. b. Tighten any loose captive installation screws on the supervisor engine and switching modules. Step 5 Connect the power supplies to the site power following the procedures in the "Removing and Replacing the Power Supply" section. (Do not turn on the power supplies at this point.) Rack-Mounting the Catalyst 5509 SwitchUse this procedure to install the Catalyst 5509 switch in a rack: Step 1 Prepare for installation as follows: a. Place the chassis on the floor or on a sturdy table as close as possible to the rack. Leave enough clearance to allow you to move around the chassis. b. Install the power supplies in the chassis by following the procedures in the "Removing and Replacing the Power Supply" section. (Do not connect the power cords at this point.) c. Use a tape measure to measure the depth of the rack. Measure from the outside of the front mounting posts to the outside of the rear mounting strip. The depth must be at least 19.25 inches (48.9 cm) but not greater than 32 inches (81.3 cm). d. Measure the space between the inner edges of the left front and right front mounting posts to ensure that it is 17.75 inches (45.09 cm) wide. (The chassis is 17.25 inches [43.8 cm] wide and must fit between the mounting posts.) e. Open the rack-mount kit and use the checklist in Table 4-3 to verify that all parts are included. Table 4-3: Catalyst 5509 Switch: Rack-Mount Kit Checklist
Step 2 Note that the two shelf brackets support the weight of the chassis in the rack. Install the shelf brackets as follows:
a. Position the shelf brackets in the rack. (See Figure 4-6.) b. Secure the shelf brackets by using six (three per side) 12-24 x 3/4-inch or 10-32 x 3/4-inch screws. c. Attach the crossbar bracket to the back of the shelf brackets using two M3 screws.
Figure 4-6: Catalyst 5509 Switch: Installing the Shelf Brackets
Step 3 Note that the L brackets connect the chassis to the rack. Install the L brackets by attaching the left and right L brackets using the eight M4 Phillips countersunk-head screws provided in the rack-mount kit. (See Figure 4-7.)
Figure 4-7: Catalyst 5509 Switch: Attaching L Brackets and Cable Guides
Step 4 Install the chassis in the rack as follows:
a. With a person standing at each side of the chassis, grasp the bottom edge of the chassis with one hand near the front and the other near the back. Slowly lift the chassis in unison. Avoid sudden twists or moves to prevent injury. b. Position the chassis in the rack as follows (see Figure 4-8):
c. Place the chassis on the shelf brackets. d. Align the mounting holes in the L bracket with the mounting holes in the equipment rack. e. A third person should install the eight (four per side) 12-24 x 3/4-inch or 10-32 x 3/4-inch screws through the elongated holes in the L bracket and into the threaded holes in the mounting post. f. Use a tape measure and level to ensure that the chassis is installed straight and level. Figure 4-8: Catalyst 5509 Switch: Installing the Switch in the Rack
Step 5 Check the ejector levers to ensure that the supervisor engine and all switching modules are installed securely. Step 6 Tighten any loose captive installation screws on the supervisor engine and switching modules. Step 7 Connect the power supplies to the site power by following the procedures in the "Removing and Replacing the Power Supply" section. (Do not turn on the power supplies at this point.) Rack-Mounting the Catalyst 5500 SwitchUse this procedure to install the Catalyst 5500 switch in a rack: Step 1 Prepare for installation as follows: a. Place the chassis on the floor or on a sturdy table as close as possible to the rack. Leave enough clearance to allow you to move around the chassis. b. Install the power supplies in the chassis by following the procedures in "Removing and Replacing the Power Supply" section. (Do not connect the power cords at this point.) c. Use a tape measure to measure the depth of the rack. Measure from the outside of the front mounting posts to the outside of the rear mounting strip. The depth must be at least 19.25 inches (48.9 cm) but not greater than 32 inches (81.3 cm). d. Measure the space between the inner edges of the left front and right front mounting posts to ensure that it is 17.75 inches (45.09 cm) wide. (The chassis is 17.25 inches [43.8 cm] wide and must fit between the mounting posts.) e. Open the rack-mount kit and use the checklist in Table 4-4 to verify that all parts are included. Table 4-4: Catalyst 5500 Switch: Rack-Mount Kit Checklist
Step 2 Note that the two shelf brackets support the weight of the chassis in the rack. Install the shelf brackets as follows:
a. Position the shelf brackets in the rack (see Figure 4-9). b. Secure the shelf brackets by using six (three per side) 12-24 x 3/4-inch or 10-32 x 3/4-inch screws. c. Attach the crossbar bracket to the back of the shelf brackets using two M3 screws.
Figure 4-9: Catalyst 5500: Installing the Shelf Brackets
Step 3 Note that the L brackets connect the chassis to the rack. Install the L brackets by attaching the left and right L brackets using the ten M4 Phillips countersunk-head screws provided in the rack-mount kit. (See Figure 4-10.)
Figure 4-10: Catalyst 5500 Switch: Attaching L Brackets and Cable Guides
Step 4 Install the chassis in the rack as follows:
a. With a person standing at each side of the chassis, grasp the bottom edge of the chassis with one hand near the front and the other near the back. Slowly lift the chassis in unison. Avoid sudden twists or moves to prevent injury. b. Position the chassis in the rack as follows (see Figure 4-11):
c. Place the chassis on the shelf brackets. d. Align the mounting holes in the L bracket with the mounting holes in the equipment rack. e. A third person should install the ten (five per side) 12-24 x 3/4-inch or 10-32 x 3/4-inch screws through the elongated holes in the L bracket and into the threaded holes in the mounting post. f. Use a tape measure and level to ensure that the chassis is installed straight and level. Figure 4-11: Catalyst 5500 Switch: Installing the Switch in the Rack
Step 5 Check the ejector levers to ensure that the supervisor engine and all switching modules are installed securely. Step 6 Tighten any loose captive installation screws on the supervisor engine and switching modules. Step 7 Connect the power supplies to the site power by following the procedures in the "Removing and Replacing the Power Supply" section. (Do not turn on the power supplies at this point.)
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|