Provides detailed instructions for device rollback and recovery.


Use this procedure to perform rollback and recovery on a device when the new software does not pass validation or the device does not boot normally.

Replace the sample values given inside the angular brackets (<...>), and use the filesystem name, such as flash: or bootflash:, as shown by the device.

Before you begin

Note
  • A rollback can reload the device and interrupt the traffic. Keep console or out-of-band access available prior to initiating the rollback procedure.

  • Do not use commands such as, emergency-install or format flash: , or perform actions such as deleting active .pkg files or clearing the install state as standard recovery steps. These actions can erase the configuration, software, and rollback information.

  • Software rollback does not automatically restore an older configuration. It may also not downgrade ROMMON, the bootloader, FPGA, or CPLD firmware.

  • Save the configuration and the complete console or session logs.

  • Confirm that a verified known-good image is available.

  • Do not remove inactive files until the rollback decision is complete.

  • Do not interrupt an install operation or power-cycle the switch.

Procedure

  1. Check the current install state of the device.

    Example:

    
    switch# show install summary
    switch# show install uncommitted
    switch# show install rollback
    switch# show boot
    switch# show version
    
  2. Identify the recovery action based on the install state of the device. Refer, Rollback conditions and recovery actions.

  3. Perform the recovery step based on the device or image condition.

    • Condition: Image is added, but not active.
      
      switch# show install summary
      Type  St   Filename/Version
      --------------------------------
      IMG   C    <current-version>
      IMG   I    <staged-version>
      

      This output shows that the current image version is still active.

      To cancel the staged change, perform this step. This command can remove the images and packages needed for a later rollback. Hence, make sure to review the proposed list of files before giving confirmation to remove the files.

      
      switch# install remove inactive
      <review the proposed deletion list>
      Do you want to remove the above files? [y/n] y
      ...
      SUCCESS: install_remove
      
    • Condition: New version is active, but not committed.

      This is the preferred rollback window.

      
      switch# show install summary
      Type  St   Filename/Version
      --------------------------------
      IMG   U    <new-version>
      
      Auto abort timer: active
      Time before rollback: <remaining-time>
      

      If validation fails, do not commit. Instead, abort the install operation. This can cause a device reload and management access might drop.

      
      switch# install abort
      This operation may require a reload of the system.
      Do you want to proceed? [y/n] y
      ...
      SUCCESS: install_abort
      

      If the command is rejected, use the install abort ? command and follow the syntax shown on the device.

      If the timer expires before the commit operation, the switch returns to the last committed state. Do not stop the timer when rollback protection is required. Stopping the timer does not commit the image.

      Check the install state after rollback:

      
      switch# show install summary
      Type  St   Filename/Version
      --------------------------------
      IMG   C    <previous-version>
      
      Auto abort timer: inactive
      
      
      switch# show install uncommitted
      No Uncommitted Packages
      

      The rejected image might still be in inactive state. Keep it until validation and log collection processes are complete.

    • Condition: New image version is already committed.

      After commit operation, the install abort option is no longer available.

      Check for a saved rollback point:

      
      switch# show install rollback
      ID    Label       Description
      ------------------------------------
      <id>  <label>     <previous-version>
      
      switch# show install rollback id <id>
      Rollback id - <id>
      IMG   C    <previous-version>
      

      Confirm the version, required files, and reload impact. You must not select a rollback ID by the number alone.

      Perform the rollback operation to the respective rollback point or ID.

      
      switch# install rollback to id <id>
      install_rollback: START
      ...
      SUCCESS: install_rollback
      

      If no usable point exists, return to the verified previous image as a new software change:

      
      switch# verify /sha512 flash:<previous-image.bin>
      switch# install add file flash:<previous-image.bin>
      switch# install activate auto-abort-timer <minutes>
      <validate after the reload>
      switch# install commit
      

      Confirm that the return path is supported. An intermediate release or configuration change might be required.

    • Condition: SMU change is uncommitted.

      For an uncommitted SMU change, perform the rollback operation to committed state.

      
      switch# install rollback to committed
      ...
      SUCCESS: install_rollback
      

      To remove a committed SMU, follow its Cisco README file.

      These are the common commands:

      
      switch# install deactivate file flash:<smu-file>
      switch# show install summary
      SMU   D    flash:<smu-file>
      
      switch# install remove file flash:<smu-file>
      

      SMU deactivation might restart processes or reload the switch.

    • Condition: Switch boots a .bin image.

      Use this only when the show version command output confirms that the switch is booting a .bin image and the product supports this method.

      
      switch# verify /sha512 flash:<previous-image.bin>
      switch# configure terminal
      switch(config)# no boot system
      switch(config)# boot system flash:<previous-image.bin>
      switch(config)# end
      switch# copy running-config startup-config
      switch# show boot
      switch# reload

      Confirm that the image is present everywhere required before reloading the device.

    • Condition: The device is in switch: prompt.
      
      switch: dir flash:
      switch: cat flash:packages.conf
      switch: boot flash:packages.conf
      

      Use the packages.conf file only when all the referenced .pkg files are present. Do not edit it manually.

      If the package set is missing or invalid, boot a verified image:

      
      switch: boot flash:<known-good-image.bin>
      

      OR

      
      switch: dir usbflash0:
      switch: boot usbflash0:<known-good-image.bin>
      

      For TFTP recovery:

      
      switch: set IP_ADDRESS <switch-ip>
      switch: set IP_SUBNET_MASK <subnet-mask>
      switch: set DEFAULT_GATEWAY <gateway-ip>
      switch: ping <tftp-server-ip>
      switch: boot tftp://<tftp-server-ip>/<known-good-image.bin>
      

      Direct .bin boot uses the bundle boot method. After IOS XE loads, copy the correct image to flash and restore the supported installation state.

  4. Validate the rollback operation using these show commands.

    Example:

    
    switch# show version
    switch# show boot
    switch# show install summary
    switch# show install uncommitted
    switch# show switch
    switch# show redundancy states
    switch# show interfaces status
    switch# show etherchannel summary
    switch# show spanning-tree summary totals
    switch# show platform resources
    switch# show environment all
    switch# show logging
    

    Confirm that

    • the intended release is active and committed

    • the rollback timer is inactive and no install operation is incomplete

    • expected members, interfaces, protocols, and services are healthy

    • CPU, memory, power, temperature, and fans are healthy, and

    • no new crash, traceback, or repeated error is present on the device.