Use this procedure to commission a Cisco APIC in the cluster using the GUI. This process is applicable to Cisco APIC releases before 6.0(2) and involves verifying the cluster's health state, commissioning the controller, and ensuring it reaches a 'Fully Fit' operational state.
Commission a Cisco APIC in the cluster using the GUI.
You typically commission a Cisco APIC when adding a new or previously decommissioned APIC to your cluster. This procedure applies to Cisco APIC releases before Cisco APIC release 6.0(2). For newer releases, refer to the subsequent section for the updated commissioning workflow.
Follow these steps to commission a Cisco APIC in the cluster:
Before you begin
-
Ensure you have an APIC controller in decommissioned state and physical access if required.
-
Confirm you have Administrator access to the Cisco APIC GUI.
Procedure
The Cisco APIC is commissioned and actively participates in the cluster with a healthy operational state.
What to do next
Monitor the cluster to ensure it maintains a healthy state. If the controller does not reach 'Active' and 'Fully Fit' status, review the configuration and attempt commissioning again.