This document describes how to install the Content Switching Module including the software and hardware requirements.
This document contains these sections:
•
Installing and Removing the Module
Physical Description
This section describes the physical attributes of the Content Switching Module:
Front Panel Description
Figure 1 shows the CSM front panel.
Figure 1 Content Switching Module Front Panel
![]()
![]()
Note
The RJ-45 connector is covered by a removable plate.
Status LED
When the CSM powers up, it initializes various hardware components and communicates with the supervisor engine. The Status LED indicates the supervisor engine operations and the initialization results. During the normal initialization sequence, the status LED changes from off to red, orange, and green.
![]()
Note
For more information on the supervisor engine LEDs, refer to the Catalyst 6500 Series Module Installation Guide.
Table 1 describes the Status LED operation.
Table 1 Content Switching Module Status LED
Color DescriptionOff
•
The module is waiting for the supervisor engine to provide power.
•
The module is not on line.
•
The module is not receiving power, which could be caused by the following:
–
Power is not available to the CSM.
–
Module temperature is over the limit1 .
Red
•
The module is released from reset by the supervisor engine and is booting.
•
If the boot code fails to execute, the LED stays red after power up.
Orange
•
The module is initializing hardware or communicating with the supervisor engine.
•
A fault occurred during the initialization sequence.
•
The module has failed to download its Field Programmable Gate Arrays (FPGAs) on power up but continues with the remainder of the initialization sequence and provides the module online status from the supervisor engine.
•
The module has not received module online status from the supervisor engine. This problem could be caused by the supervisor engine detecting a failure in an external loopback test that it issued to the CSM.
Green
•
The module is operational; the supervisor engine has provided module online status.
Green to orange
•
The module is disabled through the supervisor engine CLI 2 using the set module disable mod command.
1 Enter the show environment temperature mod command to display the temperature of each of four sensors on the CSM.
2 CLI = command-line interface.
RJ-45 Connector
The RJ-45 connector, which is covered by a removable plate, is used to connect a management station device or a test device. This connector is used by field engineers to perform testing and to obtain dump information.
Environmental Requirements
Table 2 lists the environmental requirements for the CSM:
System Requirements
Before you install the CSM into the Catalyst 6500 series switch, make sure that the switch meets the hardware and software requirements listed in this section.
![]()
CautionYou can use the MSFC, which is internal to the Catalyst 6500 series switch, to route traffic on either the client side or the server side of the CSM, but not both simultaneously (unless Policy Based Routing is used).
Memory Requirements
The CSM memory is not configurable.
Supported Hardware
Before you can use the CSM, you must have a Supervisor Engine 1A with an MSFC, a Policy Feature Card (PFC) or a Supervisor Engine 2 with an MSFC, and any module that has ports to connect server and client networks.
![]()
CautionThe WS-X6066-SLB-APC Content Switching Module is not fabric enabled, but the module can operate in a fabric-enabled chassis like any other nonfabric module.
Table 3 lists the supported hardware and software for the CSM:
Power Supply
You can place the CSM in any slot in the Catalyst 6500 series chassis except for the slots occupied by the supervisor engine and the standby supervisor engine. The CSM operates on power supplied by the chassis.
Software Requirements
![]()
CautionThe CSM cannot be used in a Catalyst 6500 series switch with the Catalyst operating system.
Table 4 lists the software versions for the CSM:
Software Compatibility
Beginning with software release 2.1(1), backward compatibility is not allowed.
If the CSM software image version you are using is more recent than the Cisco IOS software specified for that release in Table 4, you will not have all the CSM features available to you. For example, if you are running CSM software release 3.2(1) with Cisco IOS software release 12.1(11b)E, the Cisco IOS software will not have the new CLI commands that support the CSM 3.2(1) features.
If the CSM software image version you are using is older than the Cisco IOS software specified for that release in Table 4, the older CSM application software will not understand the newer IOS commands. The CSM software will still run, however the new IOS commands will have no effect.
Required Tools
These tools are required to install the module in the Catalyst 6500 series switches:
•
Flat-blade screwdriver
•
Phillips-head screwdriver
•
Wrist strap or other grounding device
•
Antistatic mat or antistatic foam
Whenever you handle the module, always use a wrist strap or other grounding device to prevent electrostatic discharge (ESD).
Installing the CSM
The following sections describe how to install the CSM:
•
Installing and Removing the Module
Preparing to Install the CSM
Before installing the CSM, make sure that the following items are available:
•
Catalyst 6500 series switch chassis
•
Management station that is available through a Telnet or a console connection to perform configuration tasks
Required Tools
These tools are required to install the module in the Catalyst 6500 series switches:
•
Flat-blade screwdriver
•
Phillips-head screwdriver
•
Wrist strap or other grounding device
•
Antistatic mat or antistatic foam
Whenever you handle the module, always use a wrist strap or other grounding device to prevent electrostatic discharge (ESD).
Installing and Removing the Module
![]()
Warning
During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly touch the backplane with your hand or any metal tool, or you could shock yourself.
All Catalyst 6500 series switches support hot swapping, which allows you to install, remove, replace, and rearrange modules without turning off the system power. For more information on removing the module from a switch, see the "Removing the Module" section.
When the system detects that a module has been installed or removed, the system automatically runs diagnostic and discovery routines, acknowledges the presence or absence of the module, and resumes system operation.
This section describes how to install and verify the operation of the Firewall Services Module in the Catalyst 6500 series switches and contains the following sections:
Slot Assignments
The Catalyst 6006 and 6506 switch chassis have six slots, the Catalyst 6009 and 6509 switch chassis have nine slots, and the Catalyst 6513 switch chassis has thirteen slots.
![]()
Note
The Catalyst 6509-NEB switch has vertical slots, which are numbered 1 to 9 from right to left. Install the modules with the component side facing to the right.
•
Slot 1 is reserved for the supervisor engine.
•
Slot 2 can be used for a redundant supervisor engine in case the supervisor engine in slot 1 fails.
•
If a redundant supervisor engine is not required, slots 2 through 6 on the 6-slot chassis, slots 2 through 9 on the 9-slot chassis, and slots 2 through 13 on the 13-slot chassis are available for switching modules, such as the Firewall Services Module.
•
The empty slots require filler plates, which are blank switching-module carriers that maintain consistent airflow through the switch chassis.
Removing the Module
This section describes how to remove an existing module from a Catalyst 6500 series switch chassis slot.
![]()
Warning
During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly touch the backplane with your hand or any metal tool, or you could shock yourself.
![]()
Warning
Before you install, operate, or service the system, read the Site Preparation and Safety Guide. This guide contains important safety information you should know before working with the system.
![]()
Warning
Invisible laser radiation may be emitted from disconnected fibers or connectors. Do not stare into beams or view directly with optical instruments.
To remove a supervisor engine or module from the chassis, perform these steps:
Step 1
Disconnect any network interface cables attached to the supervisor engine or module.
Step 2
Verify that the captive installation screws on all of the modules in the chassis are tight.
This step assures that the space created by the removed module is maintained.
![]()
Note
If the captive installation screws are loose, the electromagnetic interference (EMI) gaskets on the installed modules will push the modules toward the open slot, reducing the opening size and making it difficult to install the replacement module.
Step 3
Loosen the two captive installation screws on the supervisor engine or module.
Step 4
Depending on the orientation of the slots in the chassis (horizontal or vertical), perform one of the following set of substeps:
Horizontal slots
a.
Place your thumbs on the left and right ejector levers, and simultaneously rotate the levers outward to unseat the module from the backplane connector.
b.
Grasp the front edge of the module, and slide the module part of the way out of the slot. Place your other hand under the module to support the weight of the module. Do not touch the module circuitry.
Vertical slots
a.
Place your thumbs on the ejector levers located at the top and bottom of the module, and simultaneously rotate the levers outward to unseat the module from the backplane connector.
b.
Grasp the edges of the module, and slide the module straight out of the slot. Do not touch the module circuitry.
Step 5
Place the module on an antistatic mat or antistatic foam, or immediately reinstall it in another slot.
Step 6
If the slot from which you removed the module is to remain empty, install a module filler plate to keep dust out of the chassis and to maintain proper airflow through the chassis.
![]()
Warning
Blank faceplates (filler panels) serve three important functions: they prevent exposure to hazardous voltages and currents inside the chassis; they contain electromagnetic interference (EMI) that might disrupt other equipment; and they direct the flow of cooling air through the chassis. Do not operate the system unless all cards and faceplates are in place.
Installing a Module
This section describes how to install modules in the Catalyst 6500 series switches.
![]()
CautionTo prevent ESD damage, handle modules by the carrier edges only.
![]()
Warning
During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly touch the backplane with your hand or any metal tool, or you could shock yourself.
![]()
Warning
Invisible laser radiation may be emitted from disconnected fibers or connectors. Do not stare into beams or view directly with optical instruments.
![]()
Warning
Before you install, operate, or service the system, read the Site Preparation and Safety Guide. This guide contains important safety information you should know before working with the system.
To install a supervisor engine or module in the chassis, perform these steps:
Step 1
Choose a slot for the supervisor engine or module.
Step 2
Verify that there is enough clearance to accommodate any interface equipment that you will connect directly to the supervisor engine or module ports. If possible, place modules between empty slots that contain only module filler plates.
Step 3
Verify that the captive installation screws are tightened on all modules installed in the chassis.
This action ensures that the EMI gaskets on all modules are fully compressed in order to maximize the opening space for the replacement module.
![]()
Note
If the captive installation screws are loose, the EMI gaskets on the installed modules will push adjacent modules toward the open slot, reducing the opening size and making it difficult to install the replacement module.
Step 4
Remove the module filler plate by removing the two Phillips pan-head screws from the filler plate. (To remove a module, refer to "Removing the Module" section.)
Step 5
Fully open both ejector levers on the new or replacement module. (See Figure 0-2.)
Figure 0-2 Positioning the Module in a Horizontal Slot Chassis
![]()
Step 6
Depending on the orientation of the slots in the chassis (horizontal or vertical), perform one of the following sets of substeps:
Horizontal slots
a.
Position the supervisor engine or module in the slot. Make sure that you align the sides of the module carrier with the slot guides on each side of the slot. (See Figure 0-2.)
b.
Carefully slide the supervisor engine or module into the slot until the EMI gasket along the top edge of the module makes contact with the module in the slot above it and both ejector levers have closed to approximately 45 degrees with respect to the module faceplate. (See Figure 0-3.)
Figure 0-3 Clearing the EMI Gasket in a Horizontal Slot Chassis
![]()
c.
Using the thumb and forefinger of each hand, grasp the two ejector levers and press down to create a small (0.040 inch [1 mm]) gap between the module's EMI gasket and the module above it. (See Figure 0-3.)
![]()
CautionDo not press down too firmly on the levers. They will bend and be damaged.
d.
While pressing down, simultaneously close the left and right ejector levers to fully seat the supervisor engine or module in the backplane connector. The ejector levers are fully closed when they are flush with the module faceplate. (See Figure 0-4.)
Figure 0-4 Ejector Lever Closure in a Horizontal Slot Chassis
![]()
![]()
Note
Failure to fully seat the module in the backplane connector can result in error messages.
e.
Tighten the two captive installation screws on the supervisor engine or module.
![]()
Note
Make sure the ejector levers are fully closed before tightening the captive installation screws.
Vertical slots
a.
Position the supervisor engine or switching module in the slot. (See Figure 0-5.) Make sure that you align the sides of the switching-module carrier with the slot guides on the top and bottom of the slot.
Figure 0-5 Positioning the Module in a Vertical Slot Chassis
![]()
b.
Carefully slide the supervisor engine or module into the slot until the EMI gasket along the right edge of the module makes contact with the module in the slot adjacent to it and both ejector levers have closed to approximately 45 degrees with respect to the module faceplate. (See Figure 0-6.)
c.
Using the thumb and forefinger of each hand, grasp the two ejector levers and exert a slight pressure to the left, deflecting the module approximately 0.040 inches (1 mm) to create a small gap between the module's EMI gasket and the module adjacent to it. (See Figure 0-6.)
Figure 0-6 Clearing the EMI Gasket in a Vertical Slot Chassis
![]()
![]()
CautionDo not exert too much pressure on the ejector levers. They will bend and be damaged.
d.
While pressing on the ejector levers, simultaneously close them to fully seat the supervisor engine or module in the backplane connector. The ejector levers are fully closed when they are flush with the module faceplate. (See Figure 0-7.)
Figure 0-7 Ejector Lever Closure in a Vertical Slot Chassis
![]()
e.
Tighten the two captive installation screws on the module.
![]()
Note
Make sure the ejector levers are fully closed before tightening the captive installation screws.
This completes the CSM installation procedure.
Verifying the Installation
When you install the CSM into the Catalyst 6500 series switch, the module goes through a boot sequence that requires no intervention. At the successful conclusion of the boot sequence, the green Status LED will light and remain on. If the Status LED does not show green, or if it shows a different color, refer to Table 1 to determine the module's status.
Using the CLI
The software interface for the module is the Cisco IOS and the Catalyst operating system command-line interface accessed through a Telnet connection to the switch or through the switch console interface. Refer to the Catalyst 6500 Series IOS Software Configuration Guide and the Catalyst 6500 Series Software Configuration Guide for details.
To understand the Cisco IOS command-line interface and Cisco IOS command modes, refer to Chapter 2, "Command-Line Interfaces," in the Catalyst 6500 Series IOS Software Configuration Guide.
To understand the Catalyst operating system command-line interface and Catalyst operating system command modes, refer to Chapter 2, "Command-Line Interfaces," in the Catalyst 6500 Series Configuration Guide.
Unless your switch is located in a fully trusted environment, we recommend that you configure the module through a Telnet connection using Secure Shell (SSH) encryption.
You can session into the module from the switch console and configure the CSM. Session is a Telnet interface through the Ethernet out-of-band channel (EOBC) of the switch backplane.
You can also make a Telnet connection into the module from a specified host and on a specific interface. Telnet support for this host should be configured or enabled from the module console.
Console output is redirected to all active Telnet sessions. When no Telnet session is available, the output is saved to a buffer. The buffer output can be subsequently examined when you make a Telnet connection into the module.
Related Documentation
Use this document in conjunction with the following Cisco documents:
•
Catalyst 6500 Series IOS Software Configuration Guide
•
Catalyst 6500 Series Software Configuration Guide
•
Catalyst 6500 Series Switch Content Switching Module Command Reference Release 3.2
•
Catalyst 6500 Series Switch Content Switching Module Installation Guide Release 3.2
•
Catalyst 6500 Series Switch Content Switching Module and Installation and Configuration Guide Release 3.2
•
Release Notes for the Catalyst 6500 Series Switch Content Switching Module Release 3.2.
Obtaining Documentation
Cisco provides several ways to obtain documentation, technical assistance, and other technical resources. These sections explain how to obtain technical information from Cisco Systems.
Cisco.com
You can access the most current Cisco documentation on the World Wide Web at this URL:
http://www.cisco.com/univercd/home/home.htm
You can access the Cisco website at this URL:
International Cisco web sites can be accessed from this URL:
http://www.cisco.com/public/countries_languages.shtml
Documentation CD-ROM
Cisco documentation and additional literature are available in a Cisco Documentation CD-ROM package, which may have shipped with your product. The Documentation CD-ROM is updated monthly and may be more current than printed documentation. The CD-ROM package is available as a single unit or through an annual subscription.
Registered Cisco.com users can order the Documentation CD-ROM (product number DOC-CONDOCCD=) through the online Subscription Store:
http://www.cisco.com/go/subscription
Ordering Documentation
You can find instructions for ordering documentation at this URL:
http://www.cisco.com/univercd/cc/td/doc/es_inpck/pdi.htm
You can order Cisco documentation in these ways:
•
Registered Cisco.com users (Cisco direct customers) can order Cisco product documentation from the Networking Products MarketPlace:
http://www.cisco.com/en/US/partner/ordering/index.shtml
•
Registered Cisco.com users can order the Documentation CD-ROM (Customer Order Number DOC-CONDOCCD=) through the online Subscription Store:
http://www.cisco.com/go/subscription
•
Nonregistered Cisco.com users can order documentation through a local account representative by calling Cisco Systems Corporate Headquarters (California, U.S.A.) at 408 526-7208 or, elsewhere in North America, by calling 800 553-NETS (6387).
Documentation Feedback
You can submit comments electronically on Cisco.com. On the Cisco Documentation home page, click Feedback at the top of the page.
You can e-mail your comments to bug-doc@cisco.com.
You can submit your comments by mail by using the response card behind the front cover of your document or by writing to the following address:
Cisco Systems
Attn: Customer Document Ordering
170 West Tasman Drive
San Jose, CA 95134-9883We appreciate your comments.
Obtaining Technical Assistance
Cisco provides Cisco.com, which includes the Cisco Technical Assistance Center (TAC) Website, as a starting point for all technical assistance. Customers and partners can obtain online documentation, troubleshooting tips, and sample configurations from the Cisco TAC website. Cisco.com registered users have complete access to the technical support resources on the Cisco TAC website, including TAC tools and utilities.
Cisco.com
Cisco.com offers a suite of interactive, networked services that let you access Cisco information, networking solutions, services, programs, and resources at any time, from anywhere in the world.
Cisco.com provides a broad range of features and services to help you with these tasks:
•
Streamline business processes and improve productivity
•
Resolve technical issues with online support
•
Download and test software packages
•
Order Cisco learning materials and merchandise
•
Register for online skill assessment, training, and certification programs
To obtain customized information and service, you can self-register on Cisco.com at this URL:
Technical Assistance Center
The Cisco TAC is available to all customers who need technical assistance with a Cisco product, technology, or solution. Two levels of support are available: the Cisco TAC website and the Cisco TAC Escalation Center. The avenue of support that you choose depends on the priority of the problem and the conditions stated in service contracts, when applicable.
We categorize Cisco TAC inquiries according to urgency:
•
Priority level 4 (P4)—You need information or assistance concerning Cisco product capabilities, product installation, or basic product configuration.
•
Priority level 3 (P3)—Your network performance is degraded. Network functionality is noticeably impaired, but most business operations continue.
•
Priority level 2 (P2)—Your production network is severely degraded, affecting significant aspects of business operations. No workaround is available.
•
Priority level 1 (P1)—Your production network is down, and a critical impact to business operations will occur if service is not restored quickly. No workaround is available.
Cisco TAC Website
You can use the Cisco TAC website to resolve P3 and P4 issues yourself, saving both cost and time. The site provides around-the-clock access to online tools, knowledge bases, and software. To access the Cisco TAC website, go to this URL:
All customers, partners, and resellers who have a valid Cisco service contract have complete access to the technical support resources on the Cisco TAC website. Some services on the Cisco TAC website require a Cisco.com login ID and password. If you have a valid service contract but do not have a login ID or password, go to this URL to register:
http://tools.cisco.com/RPF/register/register.do
If you are a Cisco.com registered user, and you cannot resolve your technical issues by using the Cisco TAC website, you can open a case online at this URL:
http://www.cisco.com/en/US/support/index.html
If you have Internet access, we recommend that you open P3 and P4 cases through the Cisco TAC website so that you can describe the situation in your own words and attach any necessary files.
Cisco TAC Escalation Center
The Cisco TAC Escalation Center addresses priority level 1 or priority level 2 issues. These classifications are assigned when severe network degradation significantly impacts business operations. When you contact the TAC Escalation Center with a P1 or P2 problem, a Cisco TAC engineer automatically opens a case.
To obtain a directory of toll-free Cisco TAC telephone numbers for your country, go to this URL:
http://www.cisco.com/warp/public/687/Directory/DirTAC.shtml
Before calling, please check with your network operations center to determine the level of Cisco support services to which your company is entitled: for example, SMARTnet, SMARTnet Onsite, or Network Supported Accounts (NSA). When you call the center, please have available your service agreement number and your product serial number.
Obtaining Additional Publications and Information
Information about Cisco products, technologies, and network solutions is available from various online and printed sources.
•
The Cisco Product Catalog describes the networking products offered by Cisco Systems as well as ordering and customer support services. Access the Cisco Product Catalog at this URL:
http://www.cisco.com/en/US/products/products_catalog_links_launch.html
•
Cisco Press publishes a wide range of networking publications. Cisco suggests these titles for new and experienced users: Internetworking Terms and Acronyms Dictionary, Internetworking Technology Handbook, Internetworking Troubleshooting Guide, and the Internetworking Design Guide. For current Cisco Press titles and other information, go to Cisco Press online at this URL:
•
Packet magazine is the Cisco monthly periodical that provides industry professionals with the latest information about the field of networking. You can access Packet magazine at this URL:
http://www.cisco.com/en/US/about/ac123/ac114/about_cisco_packet_magazine.html
•
iQ Magazine is the Cisco monthly periodical that provides business leaders and decision makers with the latest information about the networking industry. You can access iQ Magazine at this URL:
http://business.cisco.com/prod/tree.taf%3fasset_id=44699&public_view=true&kbns=1.html
•
Internet Protocol Journal is a quarterly journal published by Cisco Systems for engineering professionals involved in the design, development, and operation of public and private internets and intranets. You can access the Internet Protocol Journal at this URL:
http://www.cisco.com/en/US/about/ac123/ac147/about_cisco_the_internet_protocol_journal.html
•
Training—Cisco offers world-class networking training, with current offerings in network training listed at this URL:
http://www.cisco.com/en/US/learning/le31/learning_recommended_training_list.html
This document is to be used in conjunction with the documents listed in the "Related Documentation" section.
![]()
Copyright © 2003 Cisco Systems, Inc. All rights reserved.