Installation Roadmap
This table lists the steps to install the Cisco NCS 4016 chassis and its components and prepare the system for operation. Use this table as a checklist to ensure that all components are properly installed in the correct order. For information about a step, see the respective book or section of this installation guide.
|
Step |
See |
||
|---|---|---|---|
|
Verify that the chassis is secured in the rack.
|
Cisco Network Convergence System 4000 Series Unpacking, Moving, and Securing Guide |
||
|
Ground the chassis. |
|||
|
Verify that the power components are installed. |
|||
|
Verify that the ECU/ECU2 is installed. |
|||
|
Verify that the fan trays are installed. |
|||
|
Connect the AC or DC power cord. |
|||
|
Power on the chassis. |
|||
|
Install cards and remaining components in the chassis. |
Installing Route Processor Cards, Fabric Cards, and Line Cards |
||
|
Re-install the cosmetic door. |