Table Of Contents
Turn Up Network
Before You Begin
NTP-B35 Verify Node Turn Up
NTP-B124 Provision a Point-to-Point Network
NTP-B173 Point-to-Point Network Acceptance Test
NTP-B38 Provision a Linear ADM Network
NTP-B174 Linear ADM Network Acceptance Test
NTP-B40 Provision BLSR Nodes
NTP-B126 Create a BLSR
NTP-B175 BLSR Acceptance Test
NTP-B246 Provision a Traditional BLSR Dual-Ring Interconnect
NTP-B247 Provision an Integrated BLSR Dual-Ring Interconnect
NTP-B44 Provision Path Protection Nodes
NTP-B177 Path Protection Acceptance Test
NTP-B226 Provision a Traditional Path Protection Dual-Ring Interconnect
NTP-B227 Provision an Integrated Path Protection Dual-Ring Interconnect
NTP-B248 Provision a Traditional BLSR/Path Protection Dual-Ring Interconnect
NTP-B249 Provision an Integrated BLSR/Path Protection Dual-Ring Interconnect
NTP-B230 Provision an Open-Ended Path Protection
NTP-B231 Open-Ended Path Protection Acceptance Test
NTP-B46 Subtend a Path Protection from a BLSR
NTP-B47 Subtend a BLSR from a Path Protection
NTP-B48 Subtend a BLSR from a BLSR
NTP-B172 Create a Logical Network Map
Turn Up Network
Note
The terms "Unidirectional Path Switched Ring" and "UPSR" may appear in Cisco literature. These terms do not refer to using Cisco ONS 15xxx products in a unidirectional path switched ring configuration. Rather, these terms, as well as "Path Protected Mesh Network" and "PPMN," refer generally to Cisco's path protection feature, which may be used in any topological network configuration. Cisco does not recommend using its path protection feature in any particular topological network configuration.
This chapter explains how to turn up and test a Cisco ONS 15327 network, including terminal point-to-point networks, linear add-drop multiplexers (ADMs), path protection configurations, bidirectional line switched rings (BLSRs), and subtending rings.
Before You Begin
This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).
1.
B35 Verify Node Turn Up—Complete this procedure before beginning network turn up.
2.
B124 Provision a Point-to-Point Network—Complete as needed.
3.
B173 Point-to-Point Network Acceptance Test—Complete this procedure after you create a point-to-point network.
4.
B38 Provision a Linear ADM Network—Complete as needed.
5.
B174 Linear ADM Network Acceptance Test—Complete this procedure after you create a linear ADM.
6.
B40 Provision BLSR Nodes—Complete this procedure to provision ONS 15327s in a BLSR.
7.
B126 Create a BLSR—Complete this procedure after provisioning the BLSR nodes.
8.
B175 BLSR Acceptance Test—Complete this procedure after you create a BLSR.
9.
B246 Provision a Traditional BLSR Dual-Ring Interconnect—As needed, complete this procedure after you provision a BLSR.
10.
B247 Provision an Integrated BLSR Dual-Ring Interconnect—As needed, complete this procedure after you provision a BLSR.
11.
B44 Provision Path Protection Nodes—Complete as needed.
12.
B177 Path Protection Acceptance Test—Complete this procedure after you create a path protection.
13.
B226 Provision a Traditional Path Protection Dual-Ring Interconnect—As needed, complete this procedure after you provision a path protection.
14.
B227 Provision an Integrated Path Protection Dual-Ring Interconnect—As needed, complete this procedure after you provision a path protection.
15.
B248 Provision a Traditional BLSR/Path Protection Dual-Ring Interconnect—As needed, complete this procedure after you provision a path protection and BLSR.
16.
B249 Provision an Integrated BLSR/Path Protection Dual-Ring Interconnect—As needed, complete this procedure after you provision a path protection and BLSR.
17.
B230 Provision an Open-Ended Path Protection—As needed, complete this procedure after you provision an path protection.
18.
B231 Open-Ended Path Protection Acceptance Test—As needed, complete this procedure after you provision an open-ended path protection.
19.
B46 Subtend a Path Protection from a BLSR—Complete as needed.
20.
B47 Subtend a BLSR from a Path Protection—Complete as needed.
21.
B48 Subtend a BLSR from a BLSR—Complete as needed.
22.
B172 Create a Logical Network Map—Complete as needed.
NTP-B35 Verify Node Turn Up
Purpose
|
This procedure verifies that each ONS 15327 is ready for network turn up before adding nodes to a network.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
Chapter 3, "Turn Up Node"
|
Required/As Needed
|
Required
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at any node on the network you will test. If you are already logged in, continue with Step 2.
Step 2
Click the Alarms tab.
a.
Verify that the alarm filter is not on. See the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
Step 3
Verify that the SW Version and Defaults in the node view status area match the software version and the network element (NE) defaults shown in your site plan. If any values are not correct, complete the following procedures as needed:
•
If the software is not the correct version, install the correct version from the ONS 15327 software CD. Upgrade procedures are located in a release-specific software upgrade document. Follow the upgrade procedures appropriate to the software currently installed on the node. XTC cards can also be ordered with the latest software release.
•
If the node defaults are not correct, refer to the Cisco ONS 15327 Reference Manual.
Step 4
Click the Provisioning > General tabs. Verify that all general node information settings match the settings of your site plan. If not, see the "NTP-B81 Change Node Management Information" procedure on page 9-2.
Step 5
Click the Provisioning > Timing tabs. Verify that the timing settings match the settings on your site plan. If not, see the "NTP-B85 Change Node Timing" procedure on page 9-4.
Step 6
Click the Provisioning > Network tabs. Ensure that the IP settings and other CTC network access information is correct. If not, see the "NTP-B201 Change CTC Network Access" procedure on page 9-2.
Step 7
Click the Provisioning > Protection tabs. Verify that all protection groups have been created according to your site plan. If not, see the "NTP-B203 Modify or Delete 1+1 Card Protection Settings" procedure on page 9-4.
Step 8
Click the Provisioning > Security tabs. Verify that all users have been created and their security levels and policies match the settings indicated by your site plan. If not, see the "NTP-B205 Modify Users and Change Security" procedure on page 9-5.
Step 9
If SNMP is provisioned on the node, click the Provisioning > SNMP tabs. Verify that all SNMP settings match the settings of your site plan. If not, see the "NTP-B87 Change SNMP Settings" procedure on page 9-6.
Stop. You have completed this procedure.
NTP-B124 Provision a Point-to-Point Network
Purpose
|
This procedure provisions two ONS 15327s in a point-to-point (terminal) network.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the ONS 15327 on the network where you want to provision a point-to-point configuration. If you are already logged in, continue with Step 2.
Step 2
Click the Provisioning > Protection tabs. Verify that 1+1 protection is created for the OC-N cards. Complete the "NTP-B170 Create 1+1 Protection Groups" procedure on page 3-8 if protection has not been created.
Step 3
Repeat Steps 1 and 2 for the second point-to-point node.
Step 4
Verify that the working and protect cards in the 1+1 protection groups correspond to the physical fiber connections between the nodes, that is, verify that the working card in one node connects to the working card in the other node and that the protect card in one node connects to the protect card in the other node.
Step 5
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for the working OC-N port on both point-to-point nodes. Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.
Note
DCC terminations are not provisioned on the protect ports.
Note
If the point-to-point nodes are not connected to a LAN, you will need to create the DCC terminations using a craft (direct) connection to the node. Remote provisioning is possible only after all nodes in the network have DCC terminations provisioned to in-service OC-N ports.
Step 6
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 7
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 8
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19 on both point-to-point nodes.
Step 9
Complete the "DLP-B214 Change the Service State for a Port" task on page 18-9 to put the protect card in-service.
Step 10
Verify that timing is set up at both point-to-point nodes. If not, complete the "NTP-B28 Set Up Timing" procedure on page 3-7 for one or both of the nodes. If a node uses line timing, make its working OC-N the timing source.
Step 11
Complete the "B173 Point-to-Point Network Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B173 Point-to-Point Network Acceptance Test
Purpose
|
This procedure tests a point-to-point network.
|
Tools/Equipment
|
Test set/cables appropriate to the test circuit you will create
|
Prerequisite Procedures
|
B124 Provision a Point-to-Point Network
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at one of the point-to-point nodes. If you are already logged in, continue with Step 2.
Step 2
From the View menu, choose Go to Network View.
Step 3
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export the alarm data to a file.
Step 4
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export the condition data to a file.
Step 5
On the network map, double-click a point-to-point node to open it in node view.
Step 6
Create a test circuit from the login node to the other point-to-point node:
•
For DS-1 circuits, complete the "NTP-B181 Create an Automatically Routed DS-1 Circuit" procedure on page 5-6. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For DS-3 circuits, complete the "NTP-B184 Create an Automatically Routed DS-3 Circuit" procedure on page 5-17. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For OC-N circuits, complete the "NTP-B261 Create an Automatically Routed OC-N Circuit" procedure on page 5-36. When you set the circuit state, choose IS and check the Apply to drop ports check box.
Step 7
Configure the test set for the test circuit type you created:
•
DS-1—If you are testing an unmuxed DS-1, you must have a DSX-1 panel or a direct DS-1 interface into the ONS 15327 through the AMP Champ connectors on the Mechanical Interface Card (MIC). Set the test set for DS-1. For information about configuring your test set, consult your test set user guide.
•
DS-3—If you are testing a clear channel DS-3, you must have a DSX-3 panel or a direct DS-3 interface into the ONS 15327 through the BNC connectors on the MIC. Set the test set for clear channel DS-3. For information about configuring your test set, consult your test set user guide.
•
OC-N—If you are testing an OC-N circuit, set the test set for the applicable circuit size. For information about configuring your test set, consult your test set user guide.
Step 8
Verify the integrity of all patch cables that will be used in this test by connecting one end to the test set transmit (Tx) connector and the other end to the test set receive (Rx) connector. If the test set does not run error-free, check the cable for damage and check the test set to make sure it is set up correctly before going to Step 9.
Step 9
Create a physical loopback at the circuit destination card. To do so, attach one end of a patch cable to the destination port transmit (Tx) connector; attach the other end to the port receive (Rx) connector.
Step 10
At the circuit source card:
a.
Connect the transmit (Tx) connector of the test set to the receive (Rx) connector on the circuit source card.
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector on the circuit source card.
Step 11
Verify that the test set displays a clean signal. If a clean signal is not present, repeat Steps 6 to 10 to make sure the test set and cabling are configured correctly.
Step 12
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
Step 13
Inject BIT errors from the test set. Verify that the errors display at the test set, indicating a complete end-to-end circuit.
Step 14
Complete the "DLP-B254 XTC Active/Standby Switch Test" task on page 18-40.
Step 15
Complete the "DLP-B88 Optical 1+1 Protection Test" task on page 16-67.
Step 16
Set up and complete a BER test. Use the existing configuration and follow your site requirements for the specified length of time. Record the test results and configuration.
Step 17
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
Step 18
From the View menu, choose Go to Network View.
Step 19
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export the alarm data to a file.
Step 20
Repeat Steps 9 to 19 for the other point-to-point node.
Step 21
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
Step 22
Delete the test circuit. See the "DLP-B13 Delete Circuits" task on page 16-9 for instructions.
After all tests are successfully completed and no alarms exist in the network, the network is ready for service application.
Stop. You have completed this procedure.
NTP-B38 Provision a Linear ADM Network
Purpose
|
This procedure provisions three or more ONS 15327s in a linear add-drop multiplexer (ADM) configuration.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at an ONS 15327 that you want to provision in a linear ADM network. If you are already logged in, continue with Step 2.
Figure 4-1 shows three ONS 15327s in a linear ADM configuration. In this example, working traffic flows from Slot 3/Node 1 to Slot 3/Node 2, and from Slot 2/Node 2 to Slot 2/Node 3. You create the protect path by placing Slot 3 in 1+1 protection with Slot 1 at Nodes 1 and 2, and Slot 2 in 1+1 protection with Slot 4 at Nodes 2 and 3.
Figure 4-1 Linear ADM Configuration
Step 2
Click the Provisioning > Protection tabs. Verify that 1+1 protection is created for the OC-N cards at the node. If the protection group has not been created, complete the "NTP-B170 Create 1+1 Protection Groups" procedure on page 3-8.
Step 3
Repeat Steps 1 and 2 for all other nodes that you will include in the linear ADM.
Step 4
Verify that the working and protect cards in the 1+1 protection groups correspond to the physical fiber connections between the nodes, that is, working cards are fibered to working cards and protect cards are fibered to protect cards.
Step 5
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for the working OC-N ports on each linear ADM node. Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.
Note
If linear ADM nodes are not connected to a LAN, you will need to create the DCC terminations using a craft (direct) connection to the node. Remote provisioning is possible only after all nodes that do not have LAN connections have DCC terminations provisioned to in-service OC-N ports.
Note
Terminating nodes will have one DCC termination (Nodes 1 and 3 in Figure 4-1), and intermediate nodes will have two DCC terminations (Node 2/Slot 3 and Node 2/Slot 2 in Figure 4-1).
Step 6
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 7
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 8
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19 on each linear node.
Step 9
Verify that timing has been set up at each linear node. If not, complete the "NTP-B28 Set Up Timing" procedure on page 3-7. If a node is using line timing, use its working OC-N card as the timing source.
Step 10
Complete the "B174 Linear ADM Network Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B174 Linear ADM Network Acceptance Test
Purpose
|
This procedure tests a linear ADM network.
|
Tools/Equipment
|
Test set/cables appropriate to the test circuit you will create
|
Prerequisite Procedures
|
B38 Provision a Linear ADM Network
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at an ONS 15327 on the linear ADM network you are testing. If you are already logged in, continue with Step 2.
Step 2
From the View menu choose Go to Network View.
Step 3
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 4
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 5
On the network map, double-click the linear ADM node you are testing to open it in node view.
Step 6
Create a test circuit from that node to an adjacent linear ADM node:
•
For DS-1 circuits, complete the "NTP-B181 Create an Automatically Routed DS-1 Circuit" procedure on page 5-6. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For DS-3 circuits, complete the "NTP-B184 Create an Automatically Routed DS-3 Circuit" procedure on page 5-17. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For OC-N circuits, complete the "NTP-B261 Create an Automatically Routed OC-N Circuit" procedure on page 5-36. When you set the circuit state, choose IS and check the Apply to drop ports check box.
Step 7
Configure the test set for the test circuit type you created:
•
DS-1—If you are testing an unmuxed DS-1, you must have a DSX-1 panel or a direct DS-1 interface into the ONS 15327 through the AMP Champ connectors on the MIC. Set the test set for DS-1. For information about configuring your test set, consult your test set user guide.
•
DS-3—If you are testing a clear channel DS-3, you must have a DSX-3 panel or a direct DS-3 interface into the ONS 15327 through the BNC connectors on the MIC. Set the test set for clear channel DS-3. For information about configuring your test set, consult your test set user guide.
•
OC-N—If you are testing an OC-N circuit, set the test set for the applicable circuit size. For information about configuring your test set, consult your test set user guide.
Step 8
Verify the integrity of all patch cables that will be used in this test by connecting one end to the test set transmit (Tx) connector and the other end to the test set receive (Rx) connector. If the test set does not run error-free, check the cable for damage and check the test set to make sure it is set up correctly before going to the next step.
Step 9
Create a physical loopback at the circuit destination card. To do so, attach one end of a patch cable to the destination port's transmit (Tx) connector; attach the other end to the destination port's receive (Rx) connector.
Step 10
At the circuit source card:
a.
Connect the transmit (Tx) connector of the test set to the circuit receive (Rx) connector.
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
Step 11
Verify that the test set displays a clean signal. If a clean signal is not displayed, repeat Steps 6 through 10 to make sure the test set and cabling are configured correctly.
Step 12
Inject BIT errors from the test set. Verify that the errors appear on the test set, indicating a complete end-to-end circuit.
Step 13
Complete the "DLP-B254 XTC Active/Standby Switch Test" task on page 18-40.
Step 14
Complete the "DLP-B88 Optical 1+1 Protection Test" task on page 16-67 to test the OC-N port protection group switching.
Step 15
Set up and complete a BER test. Use the existing configuration and follow your site requirements for length of time. Record the test results and configuration.
Step 16
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
Step 17
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 18
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 19
Delete the test circuit. See the "DLP-B13 Delete Circuits" task on page 16-9 for instructions.
Step 20
Repeat Steps 5 through 19 for the next linear ADM node you are testing.
Step 21
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for service application.
Stop. You have completed this procedure.
NTP-B40 Provision BLSR Nodes
Purpose
|
This procedure provisions ONS 15327 nodes for a bidirectional line switched ring (BLSR).
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B44 Install Fiber-Optic Cables for BLSR Configurations" task on page 16-34, verifying that the east port at one node is connected to the west port on an adjacent node, and this east to west port connection is used at all BLSR nodes, similar to Figure 4-2. In the figure, the OC-N drop card on the left side of the shelf is the west port, and the drop card on the right side of the shelf is the east port.
Figure 4-2 Four-Node, Two-Fiber BLSR Fiber Connection Example
Step 2
Complete the "DLP-B60 Log into CTC" task on page 16-52 at an ONS 15327 that you want to configure in a BLSR. If you are already logged in, continue with Step 3.
Step 3
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39. Provision the two ports/cards that will serve as the BLSR ports at the node.
Note
If an ONS 15327 is not connected to a corporate LAN, DCC provisioning must be performed through a craft (direct) connection to the node. Remote provisioning is possible only after all nodes in the network have DCC provisioned to in-service OC-N ports.
Step 4
Repeat Steps 2 and 3 at each node that will be in the BLSR. Verify that the EOC (DCC Termination Failure) and LOS (Loss of Signal) alarms are clear after you provision all the DCCs in the ring.
Step 5
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 6
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 7
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19 for the BLSR nodes.
Step 8
Complete the "B126 Create a BLSR" procedure.
Stop. You have completed this procedure.
NTP-B126 Create a BLSR
Purpose
|
This procedure creates a BLSR at each BLSR-provisioned node.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
B40 Provision BLSR Nodes
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite or remote
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 on an ONS 15327 node on the network where you will create the BLSR. If you are already logged in, continue with Step 2.
Step 2
Complete one of the following tasks:
•
DLP-B336 Create a BLSR Using the BLSR Wizard, page 19-34—Use this task to create the BLSR using the CTC BLSR wizard. The BLSR wizard checks to see that each node is ready for BLSR provisioning, then provisions all the nodes at once. Using the BLSR wizard is recommended.
•
DLP-B337 Create a BLSR Manually, page 19-36—Use this task to provision the BLSR manually at each node that will be in the BLSR.
Step 3
Complete the "B175 BLSR Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B175 BLSR Acceptance Test
Purpose
|
This procedure tests a two-fiber BLSR.
|
Tools/Equipment
|
Test set and cables appropriate for the test circuit
|
Prerequisite Procedures
|
B40 Provision BLSR Nodes
B126 Create a BLSR
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Note
This procedure requires that you create test circuits and perform ring switches around the ring. For clarity, "Node 1" refers to the login node where you begin the procedure. "Node 2" refers to the node connected to the east OC-N trunk (span) card of Node 1, "Node 3" refers to the node connected to the east OC-N trunk card of Node 2, and so on.
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at one of the ONS 15327s on the BLSR you are testing. (This node will be called Node 1.) If you are already logged in, continue with Step 2.
Step 2
From the View menu choose Go to Network View.
Step 3
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 4
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 5
On the network view, double-click Node 1.
Step 6
Complete the "DLP-B217 BLSR Exercise Ring Test" task on page 18-10.
Step 7
Create a test circuit from Node 1 to the node connected to the east OC-N trunk (span) card of Node 1. (This node will be called Node 2.)
•
For DS-1 circuits, complete the "NTP-B181 Create an Automatically Routed DS-1 Circuit" procedure on page 5-6. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For DS-3 circuits, complete the "NTP-B184 Create an Automatically Routed DS-3 Circuit" procedure on page 5-17. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For OC-N circuits, complete the "NTP-B261 Create an Automatically Routed OC-N Circuit" procedure on page 5-36. When you set the circuit state, choose IS and check the Apply to drop ports check box.
Step 8
Configure the test set for the test circuit type you created:
•
DS-1—If you are testing an unmuxed DS-1, you must have a DSX-1 panel or a direct DS-1 interface into the ONS 15327 through the AMP Champ connectors on the MIC. Set the test set for DS-1. For information about configuring your test set, consult your test set user guide.
•
DS-3—If you are testing a clear channel DS-3, you must have a DSX-3 panel or a direct DS-3 interface into the ONS 15327 through the BNC connectors on the MIC. Set the test set for clear channel DS-3. For information about configuring your test set, consult your test set user guide.
•
OC-N—If you are testing an OC-N circuit, set the test set for the applicable circuit size. For information about configuring your test set, consult your test set user guide.
Step 9
Verify the integrity of all patch cables that will be used in this test by connecting the test set transmit (Tx) connector to the test set receive (Rx) connector. If the test set does not run error-free, check the cable for damage and check the test set to make sure it is set up correctly before going to the next step.
Step 10
Create a physical loopback at the circuit destination card: attach one end of a patch cable to the destination port transmit (Tx) connector; attach the other end to the port receive (Rx) connector.
Step 11
At the circuit source card:
a.
Connect the transmit (Tx) connector of the test set to the circuit receive (Rx) connector.
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
Step 12
Verify that the test set displays a clean signal. If a clean signal is not present, repeat Steps 7 through 11 to make sure the test set and cabling are configured correctly.
Step 13
Inject BIT errors from the test set. Verify that the errors display at the test set, verifying a complete end-to-end circuit.
Step 14
Complete the "DLP-B254 XTC Active/Standby Switch Test" task on page 18-40.
Step 15
Complete the "DLP-B91 BLSR Ring Switch Test" task on page 16-69 at Node 1.
Step 16
Set up and complete a BER test on the test circuit. Use the existing configuration and follow your site requirements for length of time. Record the test results and configuration.
Step 17
Complete the "DLP-B13 Delete Circuits" task on page 16-9 for the test circuit.
Step 18
Repeating Steps 5 through 17 for Nodes 2 and higher, work your way around the BLSR, testing each node and span in the ring. Work your way around the BLSR creating test circuits between every two consecutive nodes.
Step 19
After you test the entire ring, remove any loopbacks and test sets from the nodes.
Step 20
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 21
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 22
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for service application. Continue with Chapter 5, "Create Circuits and VT Tunnels."
Stop. You have completed this procedure.
NTP-B246 Provision a Traditional BLSR Dual-Ring Interconnect
Purpose
|
This procedure provisions BLSRs in a traditional dual-ring interconnect (DRI) topology. DRIs interconnect two or more BLSRs to provide an additional level of protection. Two-fiber BLSRs can be mixed in a traditional BLSR DRI network.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Note
To route circuits on the DRI, you must check the Dual Ring Interconnect check box during circuit creation.
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the BLSRs that you will interconnect in a BLSR DRI. If the BLSRs are created, go to Step 3.
a.
Complete the "B40 Provision BLSR Nodes" procedure to provision the BLSRs.
b.
Complete the "B126 Create a BLSR" procedure to create the BLSRs.
c.
Complete the "B175 BLSR Acceptance Test" procedure to test two-fiber BLSRs.
Step 3
Verify that the BLSR DRI interconnect nodes have OC-N cards installed and have fiber connections to the other interconnect nodes:
•
The OC-N cards that will connect the BLSRs must be installed at the interconnect nodes.
•
The interconnect nodes must have fiber connections. Figure 4-3 shows an example of fiber connections for a traditional two-fiber BLSR DRI.
Figure 4-3 Traditional Two-Fiber BLSR DRI Fiber Connection Example
Stop. You have completed this procedure.
NTP-B247 Provision an Integrated BLSR Dual-Ring Interconnect
Purpose
|
This procedure provisions BLSRs in an integrated DRI topology.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at a node in the BLSR DRI network. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the BLSRs that you will interconnect in a BLSR DRI. If the BLSRs are created, go to Step 3.
a.
Complete the "B40 Provision BLSR Nodes" procedure to provision the BLSRs.
b.
Complete the "B126 Create a BLSR" procedure to create the BLSRs.
c.
Complete the "B175 BLSR Acceptance Test" procedure to test two-fiber BLSRs.
Step 3
Verify that the BLSR DRI interconnect node has OC-N cards installed and has fiber connections to the other interconnect node:
•
The OC-N cards that will connect the BLSRs must be installed at the two interconnect nodes.
•
The two interconnect nodes must have the correct fiber connections. Figure 4-4 shows an example of an integrated two-fiber BLSR DRI configuration.
Figure 4-4 Integrated Two-Fiber BLSR DRI Example
Stop. You have completed this procedure.
NTP-B44 Provision Path Protection Nodes
Purpose
|
This procedure provisions nodes for inclusion in a path protection. A path protection is created after the fiber connections are made.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Note
Path protection is the default ONS 15327 topology. It is available as soon as you install the path protection OC-N cards, connect the OC-N fibers, and create the DCC terminations. Unlike the BLSRs, ONS 15327 path protection configurations do not require explicit set up.
Step 1
Verify that the fiber is correctly connected to the path protection trunk (span) OC-N cards similar to Figure 4-5. See the "DLP-B43 Install Fiber-Optic Cables for Path Protection Configurations" task on page 16-31.
Figure 4-5 Path Protection Fiber Connection Example
Step 2
Complete the "DLP-B60 Log into CTC" task on page 16-52 at an ONS 15327 in the path protection you are turning up. If you are already logged in, continue with Step 3.
Step 3
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for the two cards/ports that will serve as the path protection ports on the node, for example, Slot 2 (OC-48)/Node 1 and Slot 1 (OC-48)/Node 1. (Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.)
Note
If an ONS 15327 is not connected to a corporate LAN, DCC provisioning must be performed through a craft (direct) connection. Remote provisioning is possible only after all nodes in the network have DCC terminations provisioned to in-service OC-N ports.
Step 4
Repeat Steps 2 and 3 for each node in the path protection.
Step 5
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 6
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 7
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19 at the path protection nodes.
Step 8
Complete the "B177 Path Protection Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B177 Path Protection Acceptance Test
Purpose
|
This procedure tests a path protection.
|
Tools/Equipment
|
Test set and cables appropriate to the test circuit you will create
|
Prerequisite Procedures
|
B44 Provision Path Protection Nodes
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52. If you are already logged in, continue with Step 2.
Step 2
From the View menu, choose Go to Network View.
Step 3
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 4
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 5
On the network map, double-click the node that you logged into in Step 1.
Step 6
Create a test circuit from that node to the next adjacent path protection node.
•
For DS-1 circuits, complete the "NTP-B181 Create an Automatically Routed DS-1 Circuit" procedure on page 5-6. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For DS-3 circuits, complete the "NTP-B184 Create an Automatically Routed DS-3 Circuit" procedure on page 5-17. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For OC-N circuits, complete the "NTP-B261 Create an Automatically Routed OC-N Circuit" procedure on page 5-36. When you set the circuit state, choose IS and check the Apply to drop ports check box.
Step 7
Configure the test set for the test circuit type you created:
•
DS-1—If you are testing an unmuxed DS-1, you must have a DSX-1 panel or a direct DS-1 interface into the ONS 15327 through the AMP Champ connectors on the MIC. Set the test set for DS-1. For information about configuring your test set, consult your test set user guide.
•
DS-3—If you are testing a clear channel DS-3, you must have a DSX-3 panel or a direct DS-3 interface into the ONS 15327 through the BNC connectors on the MIC. Set the test set for clear channel DS-3. For information about configuring your test set, consult your test set user guide.
•
OC-N—If you are testing an OC-N circuit, set the test set for the applicable circuit size. For information about configuring your test set, consult your test set user guide.
Step 8
Verify the integrity of all patch cables that will be used in this test by connecting one end to the test set transmit (Tx) connector and the other end to the test set receive (Rx) connector. If the test set does not run error-free, check the cable for damage and check the test set to make sure it is set up correctly before continuing.
Step 9
Create a physical loopback at the circuit destination card:
a.
Attach one end of a patch cable to the destination port transmit (Tx) connector.
b.
Attach the other end to the port receive (Rx) connector.
Step 10
At the circuit source card:
a.
Connect the transmit (Tx) connector of the test set to the circuit receive (Rx) connector.
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
Step 11
Verify that the test set displays a clean signal. If a clean signal does not appear, repeat Steps 1 through 8 to make sure the test set and cabling are configured correctly.
Step 12
Inject BIT errors from the test set. To verify that you have a complete end-to-end circuit, verify that the errors display at the test set.
Step 13
Complete the "DLP-B254 XTC Active/Standby Switch Test" task on page 18-40.
Step 14
From the View menu, choose Go to Network View.
Step 15
Click one of the two spans leaving the circuit source node and complete the "DLP-B94 Path Protection Switching Test" task on page 16-72.
Step 16
In network view, click the other circuit source span and complete the "DLP-B94 Path Protection Switching Test" task on page 16-72.
Step 17
Set up and complete a BER Test. Use the existing configuration and follow your site requirements for the length of time. Record the test results and configuration.
Step 18
Complete the "DLP-B13 Delete Circuits" task on page 16-9 for the test circuit.
Step 19
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
Step 20
Click the Alarms tab.
a.
Verify that the alarm filter is not on. Complete the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 21
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 22
Repeat Steps 6 through 21 for each node on the network.
Step 23
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for service application. Continue with Chapter 5, "Create Circuits and VT Tunnels."
Stop. You have completed this procedure.
NTP-B226 Provision a Traditional Path Protection Dual-Ring Interconnect
Purpose
|
This procedure provisions path protection configurations in a dual-ring interconnect (DRI) topology. DRIs interconnect two or more path protection configurations to provide an additional level of protection.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Note
To route circuits on the DRI, you must check the Dual Ring Interconnect check box during circuit creation.
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at any node in the path protection. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the path protection configurations that you will interconnect in a path protection DRI. If the path protection configurations are created, go to Step 3.
a.
Complete the "B44 Provision Path Protection Nodes" procedure to provision the path protection configurations.
b.
Complete the "B177 Path Protection Acceptance Test" procedure to test the path protection configurations.
Step 3
Verify that the path protection DRI interconnect nodes have OC-N cards installed and have fiber connections to the other interconnect node:
•
The OC-N cards that will connect the path protection configurations must be installed at the interconnect nodes.
•
The interconnect nodes must have fiber connections. An example is shown in Figure 4-6. This example shows a path protection DRI with two rings, Nodes 1 through 4 and 5 through 8. In the example, an additional OC-N is installed in Slot 4 at Node 4 and connected to an OC-N in Slot 2 at Node 6. Nodes 3 and 5 are interconnected with OC-N cards in Slot 2 (Node 3) and Slot 4 (Node 5).
Figure 4-6 Traditional Path Protection DRI Fiber Connection Example
Stop. You have completed this procedure.
NTP-B227 Provision an Integrated Path Protection Dual-Ring Interconnect
Purpose
|
This procedure provisions path protection configurations in an integrated DRI topology. In the integrated DRI, the path protection OC-N trunk (span) cards for both path protection configurations are installed on the same shelf.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the path protection configurations that you will interconnect in a path protection DRI. If the path protection configurations are created, go to Step 3.
a.
Complete the "B44 Provision Path Protection Nodes" procedure to provision the path protection configurations.
b.
Complete the "B177 Path Protection Acceptance Test" procedure to test the path protection configurations.
Step 3
Verify that the path protection DRI interconnect nodes have OC-N cards installed and have fiber connections to the other interconnect node:
•
The OC-N cards that will connect the path protection configurations must be installed at the interconnect nodes.
•
The interconnect nodes must have the correct fiber connections. An example is shown in Figure 4-7. This example shows a path protection DRI with two rings.
Figure 4-7 Integrated Path Protection DRI Example
Stop. You have completed this procedure.
NTP-B248 Provision a Traditional BLSR/Path Protection Dual-Ring Interconnect
Purpose
|
This procedure provisions a BLSR and a path protection in a traditional DRI topology. DRIs interconnect ring topologies to provide an additional level of protection.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Note
To route circuits on the DRI, you must check the Dual Ring Interconnect check box during circuit creation.
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the BLSR and path protection that you will interconnect in a traditional DRI. If the BLSR and path protection are created, go to Step 3.
a.
To provision and test the BLSR, complete the following procedures:
•
B40 Provision BLSR Nodes
•
B126 Create a BLSR
•
B175 BLSR Acceptance Test
b.
To provision and test the path protection, complete the following procedures:
•
B44 Provision Path Protection Nodes
•
B177 Path Protection Acceptance Test
Step 3
Verify that the DRI interconnect nodes have OC-N cards installed and have fiber connections to the other interconnect node:
•
The OC-N cards that will connect the BLSR and path protection must be installed at the interconnect nodes.
•
The interconnect nodes must have fiber connections. An example is shown in Figure 4-8.
Figure 4-8 Traditional BLSR to Path Protection DRI Fiber Connection Example
Stop. You have completed this procedure.
NTP-B249 Provision an Integrated BLSR/Path Protection Dual-Ring Interconnect
Purpose
|
This procedure provisions a BLSR and a path protection in an integrated DRI topology.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at a node in the BLSR and path protection DRI network. If you are already logged in, continue with Step 2.
Step 2
Complete the following steps if you have not provisioned the BLSR and path protection that you will interconnect in an integrated DRI. If the BLSR and path protection are created, continue with Step 3.
a.
To provision and test the BLSR, complete the following procedures:
•
B40 Provision BLSR Nodes
•
B126 Create a BLSR
•
B175 BLSR Acceptance Test
b.
To provision and test the path protection, complete the following procedures:
•
B44 Provision Path Protection Nodes
•
B177 Path Protection Acceptance Test
Step 3
Verify that the BLSR and path protection DRI interconnect nodes have OC-N cards installed and have fiber connections to the other interconnect node:
•
The OC-N cards that will connect the BLSR and path protection must be installed at the interconnect nodes.
•
The interconnect nodes must have the correct fiber connections. An example is shown in Figure 4-9.
Figure 4-9 Integrated BLSR to Path Protection DRI Example
Stop. You have completed this procedure.
NTP-B230 Provision an Open-Ended Path Protection
Purpose
|
This procedure provisions ONS 15327s in an open-ended path protection connected to a third-party vendor network. This topology allows you to route a circuit from one ONS 15327 network to another ONS 15327 network through the third-party network.
|
Tools/Equipment
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
Verify that the fiber is correctly connected to the path protection trunk (span) OC-N cards at each open-ended path protection node. Figure 4-10 shows an example. Node 1 is connected to ONS 15327 Nodes 2 and 3 through Slots 1 and Slot 3. Trunk cards at Nodes 2 and 3 are connected to the third-party vendor equipment.
Figure 4-10 ONS 15327 Open-Ended Path Protection Configurations Fiber Connection Example
Step 2
Verify that the third-party cards or units to which the ONS 15327 trunk cards are connected are the same OC-N rate as the ONS 15327 trunk cards. The third-party time slots must match the ONS 15327 card time slots to which they are connected. For example, if your trunk card is an OC-48, the third-party vendor card or unit must have STSs 1-48 available.
Step 3
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the node you are turning up. If you are already logged in, continue with Step 4.
Step 4
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for the ONS 15327 cards/ports that are connected to another ONS 15327. (Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.) Do not create a DCC termination for the card/port that connects to the third-party equipment. For example in Figure 4-10, DCC terminations are created at the following cards/ports:
•
Nodes 1 and 6: Slot 1 and Slot 3
•
Node 2 and 5: Slot 3
•
Node 3 and 4: Slot 1
Note
If an ONS 15327 is not connected to a corporate LAN, DCC provisioning must be performed through a direct (craft) connection. Remote provisioning is possible only after all nodes in the network have DCC terminations provisioned to in-service OC-N ports.
Step 5
Repeat Steps 3 and 4 for each node in the path protection.
Step 6
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 7
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 8
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19.
Step 9
Following the documentation provided by the third-party vendor, provision the optical loop leading from the ONS 15327 connection at one end to the ONS 15327 connection at the other end. In other words, you will create an open-ended path protection using procedures for the third-party equipment.
Step 10
Continue with the "B231 Open-Ended Path Protection Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B231 Open-Ended Path Protection Acceptance Test
Purpose
|
This procedure tests an open-ended path protection.
|
Tools/Equipment
|
Test set and cables appropriate to the test circuit you will create.
|
Prerequisite Procedures
|
B231 Open-Ended Path Protection Acceptance Test
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Provisioning or higher
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the node that will be the source node for traffic traversing the third-party network. If you are already logged in, continue with Step 2.
Step 2
From the View menu, choose Go to Network View.
Step 3
Click the Alarms tab.
a.
Verify that the alarm filter is not on. See the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 4
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 5
On the network map, double-click the node that you logged into in Step 1.
Step 6
Create a test circuit from that node to the OC-N trunk (span) cards on the nodes that connect to the third-party network. For example, in Figure 4-10, a circuit is created from Node 1 to the Slot 5 OC-N card at Node 2, and a secondary circuit destination is created on the Slot 12 OC-N card at Node 3. For circuit creation procedures, complete one of the following:
•
For DS-1 circuits, complete the "NTP-B181 Create an Automatically Routed DS-1 Circuit" procedure on page 5-6. When you set the circuit state, choose IS and check the Apply to drop ports check box.
•
For DS-3 circuits, complete the "NTP-B184 Create an Automatically Routed DS-3 Circuit" procedure on page 5-17. When you set the circuit state, choose IS and check the Apply to drop ports check box.
Step 7
Create a circuit within the third-party network from ONS 15327 connection ports to the second set of ONS 15327 connection ports on both path protection spans. Refer to the third-party equipment documentation for circuit creation procedures.
Step 8
Repeat Step 6 to create a second circuit at the terminating node on the other side of the third-party network. In Figure 4-10, this is Node 6. However, this circuit will have two sources, one at Node 4/Slot 12, and one at Node 5/Slot 5. The destination will be a drop card on Node 6.
Step 9
Configure the test set for the test circuit type you created:
•
DS-1—If you are testing an unmuxed DS-1, you must have a DSX-1 panel or a direct DS-1 interface into the ONS 15327. Set the test set for DS-1. For information about configuring your test set, consult your test set user guide.
•
DS-3—If you are testing a clear channel DS-3, you must have a DSX-3 panel or a direct DS-3 interface into the ONS 15327. Set the test set for clear channel DS-3. For information about configuring your test set, consult your test set user guide.
Step 10
Verify the integrity of all patch cables that will be used in this test by connecting one end to the test set transmit (Tx) connector and the other end to the test set receive (Rx) connector. If the test set does not run error-free, check the cable for damage and check the test set to make sure it is set up correctly before continuing.
Step 11
Create a physical loopback at the circuit destination card:
a.
Attach one end of a patch cable to the destination port's transmit (Tx) connector.
b.
Attach the other end to the port's receive (Rx) connector.
Step 12
At the circuit source card:
a.
Connect the transmit (Tx) connector of the test set to the circuit receive (Rx) connector.
b.
Connect the test set receive (Rx) connector to the circuit transmit (Tx) connector.
Step 13
Verify that the test set shows a clean signal. If a clean signal does not appear, repeat Steps 8 through 12 to make sure the test set and cabling are configured correctly.
Step 14
Inject BIT errors from the test set. To verify that you have a complete end-to-end circuit, verify that the errors appear at the test set.
Step 15
Complete the "DLP-B254 XTC Active/Standby Switch Test" task on page 18-40.
Step 16
From the View menu, choose Go to Network View.
Step 17
Click one of the two spans leaving the circuit source node.
Step 18
Test the path protection protection switching function on this span. Complete the "DLP-B94 Path Protection Switching Test" task on page 16-72.
Step 19
In network view, click the other circuit source span and repeat Step 18.
Step 20
Set up and complete a BER Test. Use the existing configuration and follow your site requirements for the length of time. Record the test results and configuration.
Step 21
Complete the "DLP-B13 Delete Circuits" task on page 16-9 for the test circuit.
Step 22
Remove any loopbacks, switches, or test sets from the nodes after all testing is complete.
Step 23
Click the Alarms tab.
a.
Verify that the alarm filter is not on. See the "DLP-B227 Disable Alarm Filtering" task on page 18-22 as necessary.
b.
Verify that no unexplained alarms appear on the network. If alarms are present, investigate and resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
c.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export alarm data to a file on your hard drive.
Step 24
Click the Conditions tab.
a.
Verify that the network does not have any unexplained conditions. If unexplained conditions are present, resolve them before continuing. Refer to the Cisco ONS 15327 Troubleshooting Guide if necessary.
b.
Complete the "DLP-B139 Export CTC Data" task on page 17-29 to export condition data to a file on your hard drive.
Step 25
Repeat Steps 6 through 24 for each node that will be a source or destination for circuits traversing the third-party network.
Step 26
If a node fails any test, repeat the test while verifying correct setup and configuration. If the test fails again, refer to the next level of support.
After all tests are successfully completed and no alarms exist in the network, the network is ready for service application. Continue with Chapter 5, "Create Circuits and VT Tunnels."
Stop. You have completed this procedure.
NTP-B46 Subtend a Path Protection from a BLSR
Purpose
|
This procedure subtends a path protection from an existing BLSR.
|
Tools/Equipment
|
One BLSR node must have OC-N cards and fibers to carry the path protection.
|
Prerequisite Procedures
|
B175 BLSR Acceptance Test
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
In the node that will subtend the path protection (Node 3 in Figure 4-11), install the two OC-N cards that will serve as the path protection trunk (span) cards (Node 3, Slots 3 and 4). See the "NTP-B218 Install the Optical and Ethernet Cards" procedure on page 1-11 for instructions. If they are already installed, continue with Step 2.
Step 2
Attach fibers from these cards to the path protection trunk cards on the neighbor path protection node or nodes. See the "DLP-B43 Install Fiber-Optic Cables for Path Protection Configurations" task on page 16-31 for instructions.
Step 3
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the ONS 15327 that will subtend the path protection.
Step 4
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for each OC-N card that will carry the path protection. Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.
Step 5
Log into the path protection node that connects to the node in Step 3.
Step 6
Complete the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 or the "DLP-B24 Provision Line DCC Terminations" task on page 16-21 for each OC-N card that will carry the path protection.
Step 7
Repeat Step 6 for each node in the path protection.
Step 8
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 9
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 10
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19.
Step 11
From the View menu, choose Go To Network View.
Figure 4-11 BLSR Subtending a Path Protection
Step 12
Complete the "B177 Path Protection Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B47 Subtend a BLSR from a Path Protection
Purpose
|
This procedure subtends a BLSR from an existing path protection.
|
Tools/Equipment
|
One path protection node must have OC-N cards and fibers to carry the BLSR.
|
Prerequisite Procedures
|
B177 Path Protection Acceptance Test
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Step 1
In the path protection node that will subtend the BLSR, install the two OC-N cards that will serve as the BLSR trunk (span) cards (in Figure 4-11, Node 3, Slots 1 and 2). See the "NTP-B218 Install the Optical and Ethernet Cards" procedure on page 1-11 for instructions.
Step 2
Attach fibers from the cards in Step 1 to the BLSR trunk cards on another BLSR node or nodes. In Figure 4-11, Slot 1/Node 3 connects to Slot 2/Node 2, and Slot 2/Node 3 connects to Slot 1/Node 1. See the "DLP-B44 Install Fiber-Optic Cables for BLSR Configurations" task on page 16-34 for instructions.
Step 3
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the ONS 15327 that will subtend the BLSR (the node in Step 1). If you are already logged in, continue with Step 4.
Step 4
Create the DCCs on both OC-N trunk cards (east and west) that will carry the BLSR. See the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 for instructions. Alternatively, if additional bandwidth is needed for CTC management, complete the "DLP-B24 Provision Line DCC Terminations" task on page 16-21.
Step 5
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 6
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 7
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19.
Step 8
Create the subtending BLSR:
a.
Complete the "B40 Provision BLSR Nodes" procedure for each node that will be in the BLSR. If you have already provisioned the BLSR, perform this procedure for the subtending node only.
b.
Complete the "B126 Create a BLSR" procedure. Include the node in Step 3 (the node that will subtend the BLSR) in the BLSR.
Step 9
From the View menu, choose Go to the Network View to see the subtending ring.
Stop. You have completed this procedure.
NTP-B48 Subtend a BLSR from a BLSR
Purpose
|
This procedure subtends a BLSR from an existing BLSR.
|
Tools/Equipment
|
One BLSR node must have OC-N cards and fibers needed to carry the second BLSR.
|
Prerequisite Procedures
|
None
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite
|
Security Level
|
Superuser
|
Note
This procedure assumes that all nodes are configured for the BLSR. If you need to add a node to a BLSR, see the "NTP-B102 Add a BLSR Node" procedure on page 13-2.
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at the node that will subtend the BLSR. If you are already logged in, continue with Step 2.
Step 2
Install the OC-N cards that will serve as the BLSR trunk (span) cards if they are not already installed. See the "NTP-B218 Install the Optical and Ethernet Cards" procedure on page 1-11.
Figure 4-12 shows two BLSRs shared by one ONS 15327. Ring 1 runs on Nodes 1, 2, 3, and 4. Ring 2 runs on Nodes 4, 5, 6, and 7 and represents the subtending ring added by this procedure. Two BLSR rings, Ring 1 and Ring 2, are provisioned on Node 4. Ring 1 uses cards in Slots 1 and 2, and Ring 2 uses cards in Slots 3 and 4.
Note
Although different node IDs are used for the two BLSRs shown in Figure 4-12, nodes in different BLSRs can use the same node ID.
Figure 4-12 BLSR Subtending a BLSR
Step 3
Attach fibers from the trunk cards in the subtending node to the BLSR trunk cards on its two neighboring BLSR nodes. In Figure 4-12, Node 4/Slot 3 connects to Node 7/Slot 4, and Node 4/Slot 4 connects to Node 5/Slot 3.
Step 4
Create the DCCs on the first OC-N card that will carry the BLSR. See the "DLP-B253 Provision Section DCC Terminations" task on page 18-39 or the "DLP-B24 Provision Line DCC Terminations" task on page 16-21 for instructions.
Step 5
Repeat Step 4 for the second OC-N trunk card that will carry the BLSR.
Step 6
As needed, complete the "DLP-B29 Provision a Proxy Tunnel" task on page 16-24.
Step 7
As needed, complete the "DLP-B31 Provision a Firewall Tunnel" task on page 16-26.
Step 8
As needed, complete the "DLP-B22 Create a Provisionable Patchcord" task on page 16-19.
Step 9
Complete the "B40 Provision BLSR Nodes" procedure for each node that will be in the BLSR. If you have already provisioned the BLSR, perform this procedure for the subtending node only.
Step 10
If the subtending BLSR is not already created, complete the "B126 Create a BLSR" procedure to provision the new BLSR. The subtending BLSR must have a ring name that differs from the ring name of the first BLSR. The subtending node can have one Node ID that is used in both BLSRs, or a different Node ID for each BLSR. For example, the same node can be Node 4 in BLSR 1 and Node 2 in BLSR 2.
Step 11
From the View menu choose Go to Network View to see the subtending ring.
Step 12
Complete the "B175 BLSR Acceptance Test" procedure.
Stop. You have completed this procedure.
NTP-B172 Create a Logical Network Map
Purpose
|
This procedure positions nodes in the network view. This procedure allows a superuser to create a consistent network view for all nodes on the network.
|
Tools
|
None
|
Prerequisite Procedures
|
B35 Verify Node Turn Up
This procedure also assumes that network turn up is completed.
|
Required/As Needed
|
As needed
|
Onsite/Remote
|
Onsite or remote
|
Security Level
|
Superuser
|
Step 1
Complete the "DLP-B60 Log into CTC" task on page 16-52 at any node on the network. If you are already logged in, continue with Step 2.
Step 2
From the View menu, choose Go to Network View.
Step 3
Change the position of the nodes in the network view according to your plan.
a.
Press the Ctrl key while you drag and drop a node icon to a new location.
b.
Deselect the previously selected node.
c.
Repeat Steps a and b for each node you need to position.
Step 4
On the network view map, right-click and choose Save Node Position.
Step 5
Click Yes in the Save Node Position dialog box.
CTC displays a progress bar and saves the new node positions.
Note
Retrieve, Provisioning, and Maintenance users can move nodes on the network map, but only Superusers can save new network map configurations. To restore the view to a previously saved version of the network map, right-click the network view map and choose Reset Node Position.
Stop. You have completed this procedure.