Describes the workflow for configuring a Layer 3 Outside (L3Out) network connection in ACI environments.
Summary
The key components involved in configuring ACI Layer 3 outside network connections are:
-
Administrator: Configures the L3Out network connection with proper access privileges
-
Infrastructure security domain: Provides read/write access control for configuration
-
Target leaf switches: Physical network devices with the necessary interfaces for external connectivity
-
Layer 3 Outside (L3Out): External network connection that enables routing between ACI fabric and external networks
Workflow
These are the stages of configuring ACI Layer 3 outside network connections:
-
Prerequisites: The administrator ensures proper access and infrastructure availability.
-
Ensure that you have read/write access privileges to the infra security domain.
-
Ensure that the target leaf switches with the necessary interfaces are available.
-
-
Configuration selection: The administrator chooses the appropriate L3Out scenario based on consumption requirements.
-
For an L3Out that will be consumed within a single tenant, follow the instructions for configuring BGP or OSPF.
-
For an L3Out that will be consumed (shared) among multiple tenants, follow the "Shared Layer 3 Out" guidelines.
-
For an L3Out transit routing use case, follow ACI transit routing instructions.
Note: This feature requires APIC release 1.2(1x) or later.
-