Catalyst 2926 and 2926G Series Installation Guide
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Site Planning
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Table of ContentsSite PlanningSite Environmental Requirements
Site Power Requirements General Requirements
Cabling RequirementsWarnings and Cautions EMI Recommendations Power Requirements and Heat Dissipation Network Cabling Overview
Site Planning ChecklistDetermining Cable Distances Setting Up Fast Ethernet Cabling
Connecting Interface EquipmentSetting Up Gigabit Ethernet Cabling (Catalyst 2926G Series Switch Only) Connecting the Patch Cord (Catalyst 2926GL Switch Only) Setting Up Fiber-Optic Cabling Setting Up Serial Cabling Site PlanningThis chapter describes how to prepare your site for installation of the Catalyst 2926 and Catalyst 2926G series switches. This chapter contains the following sections:
Note A site planning checklist has been provided at the end of this chapter to help ensure that all site planning activities are completed prior to switch installation. Site Environmental RequirementsYou should install your switch in an enclosed, secure area, ensuring that only qualified personnel have access to the switch and control of the environment. Equipment placed too close together or inadequately ventilated can cause system overtemperature conditions. In addition, poor equipment placement can make chassis panels inaccessible and difficult to maintain. The switch operates as a standalone system mounted in a rack in a secure wiring closet. It requires a dry, clean, well-ventilated, and air-conditioned environment. The flow of ambient air must be maintained to ensure normal operation. If the airflow is blocked or restricted, or intake air is too warm, an overtemperature condition can occur. The switch's environmental monitor can then shut down the system to protect the system components. To ensure normal operation and avoid unnecessary maintenance, plan your site configuration and prepare your site before installation. After installation, make sure the site maintains an ambient temperature of 0 to 40ºC (32 to 104ºF). It is essential to keep the area around the chassis as free from dust and foreign conductive material (such as metal flakes from nearby construction activity) as is possible. For a description of the environmental monitor and status levels, see the "Environmental Monitoring" section. Multiple switches can be rack-mounted with little or no clearance above and below the chassis. However, when mounting a switch in a rack with other equipment, or when placing it on the floor near other equipment, ensure that the exhaust from other equipment does not blow into the intake vent of the chassis. Cooling air is drawn in through the right side of the chassis. Keep the right side clear of obstructions, including dust and foreign conductive material, and away from the exhaust ports of other equipment. Appendix A, "Technical Specifications," lists the operating and nonoperating environmental site requirements for the switches. To maintain normal operation and ensure high system availability, maintain an ambient temperature and clean power at your site. The environmental ranges listed in Appendix A are within the ranges that the switch will continue to operate; however, a measurement that approaches the minimum or maximum of a range indicates a potential problem. You can maintain normal operation by anticipating and correcting environmental anomalies before they exceed the maximum operating range.
Site Power RequirementsThis section provides site power requirements. Verify your site power before you install the switch. This section consists of the following sections:
General RequirementsFollow these general requirements when preparing your site for the switch installation:
Warnings and CautionsFollow these precautions when preparing your site for the switch installation:
Note In Germany only---the electrical rating is 240 VAC and 16A.
EMI RecommendationsWhen setting up the plant wiring, consider the following factors:
Note To predict and remedy strong EMI, you might need to consult experts in RFI. Power Requirements and Heat DissipationThis section provides estimates of the power requirements and heat dissipation for the Catalyst 2926 series switch (Catalyst 2926T switch and Catalyst 2926F switch) and Catalyst 2926G series switch (Catalyst 2926GS switch and Catalyst 2926GL switch). The power requirements might be useful for planning the power distribution system needed to support the switch. Heat dissipation is an important consideration for sizing the air conditioning requirements for an installation. The power and heat associated with a Catalyst 2926 series switch and Catalyst 2926G series switch varies upon the average switching traffic levels. Unless otherwise noted, the information assumes worst-case conditions. Typical numbers are approximately 30 percent below the numbers listed here. Table 3-1 lists the power requirements and heat dissipation estimates for the Catalyst 2926T switch, which is configured as follows:
Table 3-1: Catalyst 2926T Power Requirements and Heat Dissipation
Table 3-2 lists the power requirements and heat dissipation estimates for the Catalyst 2926F switch, which is configured as follows:
Table 3-2: Catalyst 2926F Power Requirements and Heat Dissipation
Table 3-3 lists the power requirements and heat dissipation estimates for the
Cabling RequirementsThis section provides cabling guidelines for your networks using the Catalyst 2926 and Catalyst 2926G series switches. This section also describes connection equipment you will need to connect to network devices. When preparing your site for cabling to the switch, you need to consider several factors for each switch interface type. Use the following sections to determine your cabling requirements: Before installing the switch, have all cables and any additional interface equipment on hand. If you intend to build your own cables, refer to the cable pinouts in Appendix B, "Cabling Specifications." Network Cabling OverviewThe network cabling components shown in Figure 3-1 consist of the following:
Figure 3-1: Network Cabling Components
Determining Cable DistancesThe length of your networks and the distances between connections depend on the type of signal, the signal speed, and the transmission media (the type of cabling used to transmit the signals). The distance and rate limits in the following sections are the IEEE-recommended maximum speeds and distances for signaling. The distance limits in the following sections are provided as guidelines for planning your network connections before installation. Setting Up Fast Ethernet CablingThe maximum distances for Fast Ethernet network segments and connections (shown in Table 3-4) depend on the type of transmission cable used. The term 10BaseT is an abbreviation for 10 Mbps transmission, Baseband medium, and T for twisted pair. Table 3-4: Fast Ethernet Maximum Transmission Distances
Setting Up Gigabit Ethernet Cabling (Catalyst 2926G Series Switch Only)Table 3-5 provides cabling specifications for the Gigabit Ethernet uplink ports on
Connecting the Patch Cord (Catalyst 2926GL Switch Only)When connecting the 1000BaseLX/LH uplink port with 62.5-micron diameter multimode fiber (MMF), we recommend you install a mode-conditioning patch cord (Cisco product number CAB-GELX-625 or equivalent) between the uplink port and the MMF cable on both the transmit and receive ends of the link. The patch cord is required for link distances greater than 984 feet (300 meters). Otherwise, an effect called Differential Mode Delay might degrade link performance. For more information, refer to Appendix E, "Differential Mode Delay." Note We do not recommend using the Catalyst 2926GL switch with MMF and no patch cord for very short link distances (tens of meters). The result could be an elevated bit error rate (BER). Note The patch cord is required to comply with IEEE standards. The IEEE found that link distances could not be met with certain types of fiber-optic cable due to a problem in the center of some fiber-optic cable cores. The solution is to launch light from the laser at a precise offset from the center by using the patch cord. At the output of the patch cord, the 1000BaseLX/LH uplink port is compliant with the IEEE 802.3z standard for 1000BaseLX. For more information, see the "Setting Up Fiber-Optic Cabling" section. Note Cisco Gigabit Ethernet products have been tested and evaluated to comply with the standards listed in Appendix A, "Technical Specifications." Equivalent cables should also meet these standards. Patch Cord Configuration ExampleFigure 3-2 shows a typical configuration using the patch cord. Figure 3-2: Patch Cord Configuration
Patch Cord InstallationPlug the end of the patch cord labeled "To Equipment" into the uplink port (see Figure 3-3). Plug the end labeled "To Cable Plant" into the patch panel. Figure 3-3: Patch Cord Installation
Setting Up Fiber-Optic CablingThe maximum distances for fiber-optic network connections are determined by the transmitter output power, receiver sensitivity, and type of optical source, as shown in Table 3-6.
Setting Up Serial CablingAs with all signaling systems, serial signals can travel a limited distance at any given bit rate; generally, the slower the baud rate, the greater the distance. Table 3-7 shows the standard relationship between baud rate and distance for EIA/TIA-232 signals.
Connecting Interface EquipmentEthernet transceivers are available from a variety of sources for Virtual Terminal Protocol (VTP) and multimode fiber-optic cabling. Figure 3-4 shows an example of Fast Ethernet and Gigabit Ethernet transceivers and connection equipment. You might need additional data communications equipment to complete your installation. When planning your connections, consider the types and locations of connectors on adjacent switching ports to avoid overlapping the transceiver and impairing access to other connections. Figure 3-4: Fast Ethernet and Gigabit Ethernet Fiber and UTP Transceivers and Connection Equipment
Site Planning ChecklistTable 3-8 lists the site planning activities that you should perform before you install the switch. Completing each activity helps ensure a successful switch installation.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|