IMPORTANT:
This procedure assumes
that the cable management tray has been installed on the ASR 5500
chassis, and cable management brackets have been installed
on the MIO/UMIO cards.
The general procedure
for using the CMS is to route network cables, including
twisted-pair copper 1 GbE (1000Base-TX) and
fiber optic 10 GbE, through either end of the cable management
tray upwards toward the cable management brackets on the MIO/UMIOs.
Observe the following
guidelines when routing and securing network cables:
-
Label each cable with
its terminating slot/port number,
-
Insert SFP+ transceivers
in all 10 GbE ports that will receive cables.
-
Use the cable guides
on the left side of the tray for cables going to the MIO/UMIO
in slot 5, and on the right side of the tray for the MIO/UMIO
in slot 6.
-
Open the hook-and-loop
straps on the cable guides nearest the MIO/UMIOs before routing
cables.
-
Begin by routing cables
that attach at the bottom of the MIO/UMIO and proceed upward (bottom
DC to 1GbE to top DC).
-
Slip the cables beneath
the cable guides and loop them upward and within the straps along
the curved edges of the guides.
-
For 10 GbE cables, keep
cables going to even number ports to the left of the bracket, odd
number ports to the right. Use cable guide A or D for the
odd ports, and cable guide B/C or E/F
for the even number ports (see the figure below).
-
Firmly seat each cable
connector into its port.
-
Thread nylon cable
ties or hook-and-loop straps through the slots
in the cable management brackets. Use the ties/straps
to secure the cables to the brackets.
-
Complete the process
of securing the cables by closing the hook-and-loop
straps on the cable guides. Leave a little slack in the
cables to allow the tray to close without pinching the cables.
-
For additional support
of cable bundles, slip a nylon cable tie or hook-and-loop
strap under the clip at the top of a cable guide and wrap it around
the bundle.
IMPORTANT:
Verify that the cable
tray can be lifted upward and secured without pinching any of the network
cables. If necessary increase the slack in a bundle to
avoid damaging the cables.
The figure and table
below show the recommended sequence for routing cables to the MIO/UMIOs
in slots 5 and 6.
Figure 1. CMS Cable Routing
| 1 |
Cable
management bracket |
2 |
Cable
management tray |
| 3 |
Cable
guides |
. |
Table 1. CMS Routing Paths
| Card |
Cable
Guide |
Notes |
Destination |
| MIO or UMIO, slot
5 |
3A |
— |
Bottom
DC (ports 20 to 29) |
| 3A |
— |
1GbE (ports
1 and 2) |
| 3B
or 3C |
1 |
Top
DC (ports 10 to 19) |
| 3C |
2 |
Future |
| MIO or UMIO, slot
6 |
3D |
— |
Bottom
DC (ports 20 to 29) |
| 3D |
— |
1GbE (ports
1 and 2) |
| 3E
or 3F |
1 |
Top
DC (ports 10 to 19) |
| 3F |
2 |
Future |
Notes:
- If cable guide has
been removed.
- Already in use if cable
guide has been removed.