Cisco ONS 15327 Procedure Guide, Release 6.0
Chapter 10, Change Node Settings

Table Of Contents

Change Node Settings

Before You Begin

NTP-B81 Change Node Management Information

NTP-B201 Change CTC Network Information

NTP-B265 Modify OSI Provisioning

NTP-B202 Customize the CTC Network View

NTP-B203 Modify or Delete 1+1 Card Protection Settings

NTP-B85 Change Node Timing

NTP-B205 Modify Users and Change Security

NTP-B87 Change SNMP Settings

NTP-B250 Modify or Delete Communications Channel Terminations and Provisionable Patchcords


Change Node Settings


This chapter explains how to modify node provisioning for the Cisco ONS 15327. To provision a new node, see "Turn Up Node." To change default node-level settings, refer to the "B270 Edit Network Element Defaults" procedure. For a list of default settings, refer to the "Network Element Defaults" appendix in the Cisco ONS 15327 Reference Manual.


Note The terms "Unidirectional Path Switched Ring" and "UPSR" may appear in Cisco literature. These terms do not refer to using Cisco ONS 15xxx products in a unidirectional path switched ring configuration. Rather, these terms, as well as "Path Protected Mesh Network" and "PPMN," refer generally to Cisco's path protection feature, which may be used in any topological network configuration. Cisco does not recommend using its path protection feature in any particular topological network configuration.


Before You Begin

Before performing the following procedures, investigate all alarms and clear any trouble conditions. Refer to the Cisco ONS 15327 Troubleshooting Guide as necessary.

This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).

1. B81 Change Node Management Information—As needed, complete this procedure to change the node name, contact information, latitude, longitude, date, time, and login legal disclaimer.

2. B201 Change CTC Network Information—As needed, complete this procedure to change the IP address, default router, subnet mask, network configuration settings, and static routes.

3. B265 Modify OSI Provisioning—Complete this procedure as needed to modify Open System Interconnection (OSI) parameters including the OSI routing mode, Target Identifier Address Resolution Protocol (TARP), routers, subnets, and IP over OSI tunnels.

4. B202 Customize the CTC Network View—As needed, complete this procedure to customize the appearance of the network map, including specifying the default map, selecting your own map or image, and changing the background color.

5. B203 Modify or Delete 1+1 Card Protection Settings—Complete as needed.

6. B85 Change Node Timing—Complete as needed.

7. B205 Modify Users and Change Security—Complete as needed.

8. B87 Change SNMP Settings—Complete as needed.

9. B250 Modify or Delete Communications Channel Terminations and Provisionable Patchcords—Complete as needed.

NTP-B81 Change Node Management Information

Purpose

This procedure changes basic information about the node such as node name, date, time, contact information, and the login legal disclaimer.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 In node view, click the Provisioning > General tabs.

Step 4 Complete the "DLP-B140 Change the Node Name, Date, Time, and Contact Information" task, as needed.

Step 5 Complete the "DLP-B265 Change the Login Legal Disclaimer" task, as needed.

Step 6 After confirming the changes, complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B201 Change CTC Network Information

Purpose

This procedure changes essential network information, including IP settings, static routes, and Open Shortest Path First (OSPF) protocol options.

Tools/Equipment

None

Prerequisite Procedures

B169 Set Up CTC Network Access

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Note Additional ONS 15327 networking information and procedures, including IP addressing examples, static route scenarios, OSPF protocol, and routing information protocol options are provided in the "IP Networking" chapter of the Cisco ONS 15327 Reference Manual.



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 Perform the following tasks as needed:

B266 Change IP Settings

B142 Modify a Static Route

B143 Delete a Static Route

B144 Disable the Open Shortest Path First Protocol

B250 Set Up or Change Open Shortest Path First Protocol

B34 Delete a Proxy Tunnel

B35 Delete a Firewall Tunnel

Step 4 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B265 Modify OSI Provisioning

Purpose

This procedure modifies the ONS 15327 OSI parameters including the OSI routing mode, TARP, routers, subnets, and IP over CLNS tunnels.

Tools/Equipment

None

Prerequisite Procedures

B263 Provision OSI

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Note Additional information about the ONS 15327 implementation of OSI is provided in the "Management Network Connectivity" chapter of the Cisco ONS 15327 Reference Manual.



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 Perform any of the following tasks as needed:

B174 Provision or Modify TARP Operating Parameters

B175 Add a Static TID to NSAP Entry to the TARP Data Cache

B176 Remove a Static TID to NSAP Entry from the TARP Data Cache

B177 Add a TARP Manual Adjacency Table Entry

B182 Remove a TARP Manual Adjacency Table Entry

B183 Change the OSI Routing Mode

B184 Edit the OSI Router Configuration

B185 Edit the OSI Subnetwork Point of Attachment

B181 Create an IP-Over-CLNS Tunnel

B187 Delete an IP-Over-CLNS Tunnel

Step 4 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B202 Customize the CTC Network View

Purpose

This procedure modifies the CTC network view, including grouping nodes into domains for a less-cluttered display, changing the network view background color, and using a custom image for the network view background.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the following tasks, as needed:

B145 Change the Network View Background Color

B267 Change to the Default Network View Background Map

B268 Apply a Custom Network View Background Map

B148 Create Domain Icons

B149 Manage Domain Icons

B269 Enable Dialog Box Do-Not-Display Option

Stop. You have completed this procedure.


NTP-B203 Modify or Delete 1+1 Card Protection Settings

Purpose

This procedure modifies or deletes 1+1 card protection settings.

Tools/Equipment

None

Prerequisite Procedures

B170 Create 1+1 Protection Groups

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Caution Modifying and deleting protection groups can be service affecting.


Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 Perform the following tasks as needed:

B154 Modify a 1+1 Protection Group

B155 Delete a 1+1 Protection Group

Step 4 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B85 Change Node Timing

Purpose

This procedure changes the SONET timing settings for the ONS 15327.

Tools/Equipment

None

Prerequisite Procedures

B28 Set Up Timing

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 As needed, complete the "DLP-B157 Change the Node Timing Source" task.

Step 4 If you need to change any internal timing settings, follow the "DLP-B70 Set Up Internal Timing" task for the settings you need to modify.


Caution Internal timing is Stratum 3 and is not intended for permanent use. All ONS 15327s should be timed to a Stratum 2 or better primary reference source.

Step 5 If you need to verify timing after removing a node from a bidirectional line switched ring (BLSR) or a path protection, see the "DLP-B195 Verify Timing in a Reduced Ring" task.

Step 6 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B205 Modify Users and Change Security

Purpose

This procedure modifies user and security properties for the ONS 15327.

Tools/Equipment

None

Prerequisite Procedures

B30 Create Users and Assign Security

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Superuser only



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 Perform any of the following tasks as needed:

B271 Change Security Policy on a Single Node

B272 Change Security Policy on Multiple Nodes

B12 Change Node Access and PM Clearing Privilege

B158 Change User Password and Security Settings on a Single Node

B160 Change User Password and Security Settings on Multiple Nodes

B159 Delete a User on a Single Node

B161 Delete a User on Multiple Nodes

Step 4 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B87 Change SNMP Settings

Purpose

This procedure modifies Simple Network Management Protocol (SNMP) settings for the ONS 15327.

Tools/Equipment

None

Prerequisite Procedures

B171 Set Up SNMP

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Superuser only



Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 Complete the "B108 Back Up the Database" procedure.

Step 3 Perform the following tasks as needed:

B273 Modify SNMP Trap Destination

B163 Delete SNMP Trap Destinations

Step 4 Complete the "B108 Back Up the Database" procedure.

Stop. You have completed this procedure.


NTP-B250 Modify or Delete Communications Channel Terminations and Provisionable Patchcords

Purpose

This procedure changes or deletes section data communication channels (SDCCs) and line data communication channels (LDCCs), and deletes provisionable patchcords (PPCs) on the ONS 15327.

Tools/Equipment

None

Prerequisite Procedures

B253 Provision Section DCC Terminations

B24 Provision Line DCC Terminations

B22 Create a Provisionable Patchcord

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Caution Deleting a DCC termination can cause you to lose visibility of nodes that do not have other DCCs or network connections to the CTC computer.


Step 1 Complete the "DLP-B60 Log into CTC" task. If you are already logged in, continue with Step 2.

Step 2 As needed, complete the following tasks to modify data communication channel settings:

To modify an SDCC termination, complete the "DLP-B25 Change a Section DCC Termination" task.

To modify an LDCC termination, complete the "DLP-B26 Change a Line DCC Termination" task.

Step 3 As needed, complete the following tasks to delete data communication channel terminations:

To delete a SDCC termination, complete the "DLP-B27 Delete a Section DCC Termination" task.

To delete an LDCC termination, complete the "DLP-B28 Delete a Line DCC Termination" task.

Step 4 As needed, to delete a provisioning patchcord complete the "DLP-B23 Delete a Provisionable Patchcord" task.

Stop. You have completed this procedure.