The documentation set for this product strives to use bias-free language. For the purposes of this documentation set, bias-free is defined as language that does not imply discrimination based on age, disability, gender, racial identity, ethnic identity, sexual orientation, socioeconomic status, and intersectionality. Exceptions may be present in the documentation due to language that is hardcoded in the user interfaces of the product software, language used based on RFP documentation, or language that is used by a referenced third-party product. Learn more about how Cisco is using Inclusive Language.
The switch requires a operating temperature of 32 to 104° F (0 to 40° C). If the switch is not operating, the temperature must be between –40 to 158° F (–40 to 70° C).
High humidity can cause moisture to enter the switch. Moisture can cause corrosion of internal components and degradation of properties such as electrical resistance, thermal conductivity, physical strength, and size. The switch is rated to operate at 8 to 80 percent relative humidity, with a humidity gradation of 10 percent per hour. For nonoperating conditions, the switch can withstand from 5 to 95 percent relative humidity. Buildings in which the climate is controlled by air-conditioning in the warmer months and by heat during the colder months usually maintain an acceptable level of humidity for the switch equipment. However, if the switch is located in an unusually humid location, you should use a dehumidifier to maintain the humidity within an acceptable range.
If you operate a switch at a high altitude (low pressure), the efficiency of forced and convection cooling is reduced and can result in electrical problems that are related to arcing and corona effects. This condition can also cause sealed components with internal pressure, such as electrolytic capacitors, to fail or to perform at a reduced efficiency. This switch is rated to operate at altitudes from –500 to 13,123 feet (–152 to 4,000 meters). You can store the switch at altitudes of –1,000 to 30,000 feet (–305 to 9,144 meters).
Exhaust fans cool power supplies and system fan trays cool switches by drawing in air and exhausting air out through various openings in the chassis. However, fans also ingest dust and other particles, causing contaminant buildup in the switch and increased internal chassis temperature. A clean operating environment can greatly reduce the negative effects of dust and other particles, which act as insulators and interfere with the mechanical components in the switch.
Electromagnetic interference (EMI) and radio frequency interference (RFI) from the switch can adversely affect other devices such as radio and television (TV) receivers operating near the switch. Radio frequencies that emanate from the switch can also interfere with cordless and low-power telephones. Conversely, RFI from high-power telephones can cause spurious characters to appear on the switch monitor.
RFI is defined as any EMI with a frequency above 10 kHz. This type of interference can travel from the switch to other devices through the power cable and power source or through the air like transmitted radio waves. The Federal Communications Commission (FCC) publishes specific regulations to limit the amount of EMI and RFI that can be emitted by computing equipment. Each switch meets these FCC regulations.
Bad wiring can result in radio interference emanating from the plant wiring.
Strong EMI, especially when it is caused by lightning or radio transmitters, can destroy the signal drivers and receivers in the chassis and even create an electrical hazard by conducting power surges through lines into equipment.
Note | To predict and prevent strong EMI, you might need to consult experts in radio frequency interference (RFI). |
The wiring is unlikely to emit radio interference if you use twisted-pair cable with a good distribution of grounding conductors. If you exceed the recommended distances, use a high-quality twisted-pair cable with one ground conductor for each data signal when applicable.
Caution | If the wires exceed the recommended distances, or if wires pass between buildings, give special consideration to the effect of a lightning strike in your vicinity. The electromagnetic pulse caused by lightning or other high-energy phenomena can easily couple enough energy into unshielded conductors to destroy electronic switches. You might want to consult experts in electrical surge suppression and shielding if you had similar problems in the past. |
The switch has been shock- and vibration-tested for operating ranges, handling, and earthquake standards.
The switch is sensitive to variations in voltage supplied by the power sources. Overvoltage, undervoltage, and transients (or spikes) can erase data from the memory or cause components to fail. To protect against these types of problems, ensure that there is an earth-ground connection for the switch. You can connect the grounding pad on the switch either directly to the earth-ground connection or to a fully bonded and grounded rack.
You must provide the grounding cable to make this connection, but you can connect the grounding wire to the switch using a grounding lug that ships with the switch. Size the grounding wire to meet local and national installation requirements. Depending on the power supply and system, a 12 AWG to 6 AWG copper conductor is required for U.S. installations (for those installations, we recommend that you use commercially available 6 AWG wire). The length of the grounding wire depends on the proximity of the switch to proper grounding facilities.
Note | You automatically ground the AC power supplies when you connect them to a power source. You must also connect the chassis to the facility earth ground. |
To plan for the power requirements of a switch, you must determine each of the following:
Power requirements for all of the switch components
Minimum number of power supplies required to power the components installed in the switch
Power mode to use and the number of additional power supplies required for that mode
You must also ensure that the circuit used for the switch is dedicated to the switch to minimize the possibility of circuit failure.
When you know the amount of power that is required for operations (available power) and redundancy (reserve power), you can plan for the required number of input power receptacles within reach of the switch location.
You can install the following types of racks or cabinets for your switch:
Standard perforated cabinets
Solid-walled cabinets with a roof fan tray (bottom to top cooling)
Standard open four-post Telco racks
To correctly install the switch in a cabinet that is located in a hot-aisle/cold-aisle environment, you should fit the cabinet with baffles to prevent exhaust air from recirculating into the chassis air intake.
Work with your cabinet vendors to determine which of their cabinets meet the following requirements or see the Cisco Technical Assistance Center (TAC) for recommendations:
Use a standard 19-inch (48.3 cm), four-post Electronic Industries Alliance (EIA) cabinet or rack with mounting rails that conform to English universal hole spacing per section 1 of the ANSI/EIA-310-D-1992 standard.
The height of the rack or cabinet must accommodate the 7.1-RU (12.4 inches or 31.6 cm) height of the switch and its bottom support bracket.
The depth of a four-post rack must be 24 to 32 inches (61.0 to 81.3 cm) between the front and rear mounting brackets.
Required clearances between the chassis and the edges of its rack or the interior of its cabinet are as follows:
4.5 inches (11.4 cm) between the front of the chassis and the front of the rack or interior of the cabinet (required for cabling).
3.0 inches (7.6 cm) between the rear of the chassis and the interior of the cabinet (required for airflow in the cabinet if used).
No clearance is required between the chassis and the sides of the rack or cabinet (no side airflow).
Additionally, you must consider the following site requirements for the rack:
Power receptacles must be located within reach of the power cords used with the switch.
Power cords for 3-kW AC power supplies are 8 to 12 feet (2.5 to 4.3 m) long. For the power cord specifications, see AC Power Cord Specifications.
Clearance is required for cables that connect to as many as 192 ports (in addition to the cabling required for other devices in the same rack). These cables must not block access to any removable chassis modules or block airflow into or out of the chassis. Route the cables through the cable management frames on the left and right sides of the chassis.
Warning | Statement 1048—Rack Stabilization Stability hazard. The rack stabilizing mechanism must be in place, or the rack must be bolted to the floor before you slide the unit out for servicing. Failure to stabilize the rack can cause the rack to tip over. |
You must provide the chassis with adequate clearance between the chassis and any other rack, device, or structure so that you can properly install the chassis, route cables, provide airflow, and maintain the switch. For the clearances required for an installation of this chassis, see the following figure.
1 |
Chassis |
9 |
Rear service clearance required to replace fan trays and fabric modules |
2 |
Vertical rack-mount posts and rails |
10 |
Clearance area required at the rear of the chassis within the cabinet (if used) or to the edge of the hot aisle (if no cabinet) for module handles |
3 |
Nearest object or inside of cabinet (no side clearance required) |
11 |
Chassis depth |
4 |
Air intake from the cold aisle for all modules and power supplies |
12 |
Clearance required between the front of the chassis and the inside of the cabinet (if used) or the edge of the cold aisle (if no cabinet) for cable management and ejector handles on I/O modules |
5 |
Air exhaust to the hot aisle for all modules and power supplies |
13 |
Front service clearance required for installing the chassis and replacing the modules on the front of the chassis |
6 |
No left side clearance required (no airflow on left side) |
14 |
Width of the chassis plus vertical mounting brackets on each side |
7 |
Chassis width |
15 |
Side clearance required by the front of the chassis for rotation of I/O module handles (keep this area clear of rack, cable management, and other components that can prevent full rotation of the ejector levers) |
8 |
No right side clearance required (no airflow on right side) |