Cisco MDS 9500 Series Hardware Installation Guide
Site Planning and Maintenance Records
Downloads: This chapterpdf (PDF - 3.12MB) The complete bookPDF (PDF - 35.92MB) | Feedback

Site Planning and Maintenance Records

Table Of Contents

Site Planning and Maintenance Records

Contacting Customer Service

Finding the Chassis Serial Number

Site Preparation Checklist

Contact and Site Information

Chassis and Module Information


Site Planning and Maintenance Records


This appendix provides a Site Planning list and includes the following records to use when installing the Cisco MDS 9500 Series:

Contacting Customer Service

Site Preparation Checklist

Contact and Site Information

Chassis and Module Information


Note For information on how to query the switch for configuration information, see Cisco MDS 9000 Family NX-OS Fundamentals Configuration Guide or the Cisco DCNM SAN Fundamentals Configuration Guide.


Contacting Customer Service

If you are unable to solve a startup problem after using the troubleshooting suggestions in this appendix, contact your customer service representative for assistance and further instructions. Before you call, have the following information ready to help your service provider assist you as quickly as possible:

Date you received the switch.

Chassis serial number. See the "Finding the Chassis Serial Number" section.

Type of software and release number.

Maintenance agreement or warranty information.

Brief description of the problem.

Brief explanation of the steps you have already taken to isolate and resolve the problem.


Note If you purchased Cisco support through a Cisco reseller, contact the reseller directly. If you purchased support directly from Cisco, contact Cisco Technical Support at this URL: http://www.cisco.com/en/US/support/tsd_cisco_worldwide_contacts.html


Finding the Chassis Serial Number


Tip If you have CLI access, enter the show sprom backplane 1 command to display the backplane contents, including the switch serial number.


Figure F-1 shows the location of the serial number label on the Cisco MDS 9513 Director.

Figure F-1 Serial Number Location on Cisco MDS 9513 Director

In later releases of the Cisco MDS 9509 Director, the chassis serial number label was moved, as shown in Figure F-2. Earlier releases may have the serial number label on the right side instead of the left.

Figure F-2 Serial Number Location on Cisco MDS 9509 Director

The Cisco MDS 9506 Director chassis serial number label is shown in Figure F-3.

Figure F-3 Serial Number Location on Cisco MDS 9506 Director

Site Preparation Checklist

Planning the location and layout of your equipment rack or wiring closet is essential for successful switch operation, ventilation, and accessibility. Table F-1 lists the site planning tasks that Cisco recommends completing before installing the Cisco MDS 9500 Series.

Consider heat dissipation when sizing the air-conditioning requirements for an installation. See Table D-1 on page D-1 for the environmental requirements. See the"Power Specifications for the Cisco MDS 9513 Director" section on page D-6, the "Power Specifications for the Cisco MDS 9509 Director" section on page D-10, and the "Power Specifications for the Cisco MDS 9506 Director" section on page D-15 for power and heat ratings.

Table F-1 Site Planning Checklist 

Task No.
Planning Activity
Verified By
Time
Date

1

Space evaluation:

Space and layout

Floor covering

Impact and vibration

Lighting

Maintenance access

     

2

Environmental evaluation:

Ambient temperature

Humidity

Altitude

Atmospheric contamination

Air flow

     

3

Power evaluation:

Input power type

Power receptacles (20 A)1

Receptacle proximity to the equipment

Dedicated (separate) circuits for redundant power supplies

UPS2 for power failures

DC systems: proper gauge wire and lugs

     

4

Grounding evaluation:

Circuit breaker size

CO ground (AC- and DC-powered systems)

     

5

Cable and interface equipment evaluation:

Cable type

Connector type

Cable distance limitations

Interface equipment (transceivers)

     

6

EMI3 evaluation:

Distance limitations for signaling

Site wiring

RFI4 levels

     

1 Verify that each power supply installed in the chassis has a dedicated AC source or DC source circuit.

2 UPS = uninterruptible power supply

3 EMI = electromagnetic interference

4 RFI = radio frequency interference


Contact and Site Information

Use the following worksheet (Table F-2) to record contact and site information.

Table F-2 Contact and Site Information 

Contact person
 
Contact phone
 
Contact e-mail
 
Building/site name

 

Data center location

 

Floor location
 
Address (line 1)
 
Address (line 2)
 
City

 

State
 
Zip code
 
Country
 

Chassis and Module Information

Use the following worksheets (Table F-3 and Table F-4) to record information about the chassis and modules.

Contract number_______________________________________________

Chassis serial number___________________________________________

Product number________________________________________________

Table F-3 Network-Related Information 

Switch IP address
 
Switch IP netmask
 
Host name
 
Domain name
 
IP broadcast address
 
Gateway/router address
 
DNS address
 
Modem telephone number
 

Table F-4 Module Information 

Slot
Module Type
Module Serial Number
Notes
1
 

 

 

2
 

 

 

3
 

 

 

4
 

 

 

5
Supervisor
 

 

6
Supervisor
 

 

7
 

 

 

8
 

 

 

9
 

 

 



Note Slots 7, 8, and 9 are only available in the Cisco MDS 9509 Director.